2631 S CASTLE HEIGHTS PL 90034

Certificate Information: 2631 S CASTLE HEIGHTS PL 90034

Application / Permit
23014-30000-05383
Plan Check / Job No.
B23WL03185
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2nd floor addition and remodel to (e) 1-story SFD , add a new attached 2-car garage
Permit Issued
Issued on 10/4/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 YASHAR EMAMI
Corrections Issued 1/18/2024 YASHAR EMAMI
Quality Review Completed 1/19/2024 REZA HAGHIGHAT
Building Plans Picked Up 1/22/2024 APPLICANT
Applicant returned to address corrections 4/26/2024 YASHAR EMAMI
Plan Check Approved 9/10/2024 YASHAR EMAMI
Issued 10/4/2024 APPLICANT
CofO in Progress 11/14/2025 ASHLEY THOMPSON
Permit Finaled 11/19/2025 RICHARD STEINBACH
Permit Finaled 11/19/2025 RICHARD STEINBACH
CofO Issued 11/19/2025 RICHARD STEINBACH

Permit Application Clearance Information

ZA Case Cleared 1/23/2024 JAZMIN ROQUE
Permit Cleared 1/24/2024 DARIN LAM
Roof/Waste drainage to street Cleared 1/24/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 2/26/2024 DARIN LAM
Sewer availability Cleared 2/26/2024 DARIN LAM
GPI Written Notices Cleared 4/26/2024 YASHAR EMAMI
Grading Pre-Inspection Cleared 4/26/2024 YASHAR EMAMI
Trees in Parkway Cleared 8/8/2024 DYNL MIRANDA

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/13/2024 Corrections Issued ASHLEY THOMPSON
METHANE-Barrier 11/13/2024 Approved ASHLEY THOMPSON
METHANE-Subgrade 11/13/2024 Approved ASHLEY THOMPSON
Footing/Foundation/Slab 11/18/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 12/3/2024 Corrections Issued ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 12/3/2024 Corrections Issued ASHLEY THOMPSON
Green Building Rough 12/3/2024 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Rough 12/3/2024 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 12/6/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 1/13/2025 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Partial Approval SEAN HAUPT
Green Building Rough 1/13/2025 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 1/13/2025 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 1/13/2025 Not Ready for Inspection SEAN HAUPT
Deputy Wood Construction 1/15/2025 Conditional Approval KIRK SANDERS
HVAC-Rough 1/15/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 1/15/2025 Corrections Issued KIRK SANDERS
HVAC-Rough 1/16/2025 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 1/16/2025 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 1/22/2025 Not Ready for Inspection KIRK SANDERS
Green Building Rough 1/22/2025 Not Ready for Inspection KIRK SANDERS
Pre-Inspection 1/27/2025 Not Ready for Inspection MEL KHACHATOURIAN
Insulation 2/6/2025 Approved EVAN COOPER
Drywall Nailing 2/11/2025 Partial Inspection JAYLIN GRAVITTE
Green Building Rough 2/11/2025 Partial Inspection JAYLIN GRAVITTE
Interior/Exterior Lathing 2/11/2025 Partial Inspection JAYLIN GRAVITTE
Special/Order Compliance 2/11/2025 Partial Inspection ASHLEY THOMPSON
BUILDING-Rough-Frame 2/12/2025 Conditional Approval ASHLEY THOMPSON
Drywall Nailing 2/12/2025 Conditional Approval ASHLEY THOMPSON
Final 2/12/2025 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 2/12/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 2/12/2025 Partial Approval ASHLEY THOMPSON
PLUMBING-Rough 2/12/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 3/11/2025 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 4/1/2025 Corrections Issued ARAM AVEDISIAN
Interior/Exterior Lathing 4/3/2025 Partial Approval STEPHANIE SWANSON
Deputy Drilled-In Anchors 4/25/2025 Conditional Approval ASHLEY THOMPSON
PLUMBING-Final 5/13/2025 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 5/14/2025 Corrections Issued ASHLEY THOMPSON
HVAC-Final 5/29/2025 Corrections Issued MEL KHACHATOURIAN
HVAC-Final 6/2/2025 Corrections Issued TEMISTOCLES CAAL
BUILDING-Rough-Frame 6/9/2025 Approved EVAN COOPER
Drywall Nailing 6/9/2025 Approved EVAN COOPER
Final 6/9/2025 Corrections Issued EVAN COOPER
Green Building Final 6/9/2025 Approved EVAN COOPER
Green Building Rough 6/9/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 6/9/2025 Approved EVAN COOPER
Final 11/14/2025 OK to Issue CofO ASHLEY THOMPSON