2001-2003 S PARNELL AVE 90025
Certificate Information: 2001-2003 S PARNELL AVE 90025
- Application / Permit
- 23014-30000-05378
- Plan Check / Job No.
- B23WL03177
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- major remodel of (e) S.F.R. , addition of 2nd floor with addatched garage and new attached ADU per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 5/13/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 5/13/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2024 | YASHAR EMAMI |
| Corrections Issued | 1/9/2024 | YASHAR EMAMI |
| Quality Review Completed | 1/17/2024 | REZA HAGHIGHAT |
| Building Plans Picked Up | 1/17/2024 | APPLICANT |
| Applicant returned to address corrections | 2/20/2025 | YASHAR EMAMI |
| Applicant returned to address corrections | 4/16/2025 | YASHAR EMAMI |
| Plan Check Approved | 4/25/2025 | YASHAR EMAMI |
| Issued | 5/13/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2024 | KIMBERLY HERNANDEZ |
| Sewer availability | Cleared | 7/2/2024 | KIMBERLY HERNANDEZ |
| Specific Plan | Cleared | 11/14/2024 | RICHARD WOO |
| Address approval | Cleared | 12/17/2024 | HISASHI KOBAYAKAWA |
| Low Impact Development (LID) | Cleared | 12/17/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/17/2024 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 5/9/2025 | DIANA RENTERIA |
| Trees in Parkway | Cleared | 5/9/2025 | MIGUEL ORNELAS |
| GPI Written Notices | Cleared | 5/13/2025 | YASHAR EMAMI |
| Grading Pre-Inspection | Cleared | 5/13/2025 | YASHAR EMAMI |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Namdar,, Mansour; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 6/16/2025 | Partial Approval | DANIEL VERA |
| Underground Mechanical | 6/16/2025 | Partial Approval | DANIEL VERA |
| Sewer | 6/17/2025 | Partial Approval | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 6/24/2025 | Corrections Issued | DANIEL VERA |
| Footing/Foundation/Slab | 6/24/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Barrier | 6/24/2025 | Not Ready for Inspection | DANIEL VERA |
| METHANE-Subgrade | 6/24/2025 | Not Ready for Inspection | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 6/26/2025 | Approved | DANIEL VERA |
| Footing/Foundation/Slab | 6/26/2025 | Approved | DANIEL VERA |
| METHANE-Barrier | 6/26/2025 | Approved | DANIEL VERA |
| METHANE-Subgrade | 6/26/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2025 | Corrections Issued | DANIEL VERA |
| METHANE-Rough | 8/27/2025 | Partial Approval | DANIEL VERA |
| PLUMBING-Rough | 8/27/2025 | Approved | DANIEL VERA |
| Underground Mechanical | 8/27/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2025 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2025 | Not Ready for Inspection | DANIEL VERA |
| Wood Frame | 9/18/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2025 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Not Ready | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 9/25/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 9/25/2025 | Corrections Issued | DANIEL VERA |
| Wood Frame | 9/25/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 10/7/2025 | Corrections Issued | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 10/7/2025 | Conditional Approval | DANIEL VERA |
| Wood Frame | 10/7/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 10/9/2025 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Approved | DANIEL VERA |
| Wood Frame | 10/9/2025 | Approved | DANIEL VERA |
| BUILDING-Rough-Frame | 11/12/2025 | Conditional Approval | MICHAEL ALLEN |
| Green Building Rough | 11/12/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | MICHAEL ALLEN |
| METHANE-Rough | 11/12/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 11/25/2025 | Approved | DANIEL VERA |
| Insulation | 11/25/2025 | Partial Approval | DANIEL VERA |
| Interior/Exterior Lathing | 11/25/2025 | Partial Approval | DANIEL VERA |
| Insulation | 12/1/2025 | Approved | DANIEL VERA |
| Shower Pan | 12/1/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 12/8/2025 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 12/8/2025 | Approved | SEAN HAUPT |