603 1/2 N HIGHLAND AVE 90036
Certificate Information: 603 1/2 N HIGHLAND AVE 90036
- Application / Permit
- 23014-30000-05204
- Plan Check / Job No.
- B23WL03109
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition and conversion of (e) detached garage to an ADU per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 6/23/2025
- Issuing Office
- Metro
- Current Status
- Issued on 6/23/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2024 | YASHAR EMAMI |
| Corrections Issued | 1/11/2024 | YASHAR EMAMI |
| Quality Review Completed | 1/16/2024 | REZA HAGHIGHAT |
| Building Plans Picked Up | 1/22/2024 | APPLICANT |
| Applicant returned to address corrections | 5/31/2024 | YASHAR EMAMI |
| Plan Check Approved | 8/5/2024 | YASHAR EMAMI |
| Issued | 6/23/2025 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 1/23/2024 | JAZMIN ROQUE |
| Address approval | Cleared | 1/26/2024 | ANTHONY TRAN |
| Roof/Waste drainage to street | Cleared | 1/26/2024 | ANTHONY TRAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2024 | ANTHONY TRAN |
| Sewer availability | Cleared | 3/29/2024 | ANTHONY TRAN |
| HPOZ | Cleared | 5/10/2024 | SUKI GERSHENHORN |
Contact Information
| Contractor | Oracle Construction Services Inc; Lic. No.: 1090821-B | 1702 S ROBERTSON BLVD STE 267 LOS ANGELES, CA 90035 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/27/2025 | Approved | DAVID WILLIAMS |
| Deck | 7/11/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 7/11/2025 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/11/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 7/11/2025 | Approved | CRAIG VAUGHAN |
| Protected Tree Letter | 7/11/2025 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/14/2025 | Corrections Issued | CRAIG VAUGHAN |
| METHANE-Barrier | 7/14/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| METHANE-Subgrade | 7/14/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/18/2025 | Corrections Issued | CRAIG VAUGHAN |
| Underground Mechanical | 7/18/2025 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/22/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/22/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 12/22/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 12/22/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| METHANE-Rough | 12/22/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/22/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/29/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/29/2025 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2025 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 12/29/2025 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/29/2025 | Corrections Issued | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 12/29/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 12/29/2025 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/31/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 12/31/2025 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 12/31/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/31/2025 | Corrections Issued | CRAIG VAUGHAN |
| Insulation | 1/27/2026 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 1/27/2026 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 2/3/2026 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/6/2026 | Approved | CRAIG VAUGHAN |