1031 E MARCO PL 90291
Certificate Information: 1031 E MARCO PL 90291
- Application / Permit
- 23014-30000-04993
- Plan Check / Job No.
- B23WL02987
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1-STORY ADDITION AND NEW ROOF TO PART OF EXISTING 1-STORY SFD
- Permit Issued
- Issued on 12/21/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2023 | RICHARD GARCIA |
| Corrections Issued | 12/12/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 12/14/2023 | APPLICANT |
| Plan Check Approved | 12/21/2023 | JOHNPAUL ISIP |
| Issued | 12/21/2023 | APPLICANT |
| CofO in Progress | 7/12/2024 | HERBERT GIRON |
| Permit Finaled | 7/15/2024 | DANIEL ORRANTE |
| CofO Issued | 7/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2023 | BRENDEN HAWK |
| Specific Plan | Cleared | 12/18/2023 | ALESSANDRO MERCURI |
| Roof/Waste drainage to street | Cleared | 12/19/2023 | ANTHONY MAINEZ |
Contact Information
| Contractor | Handshake Builders Llc; Lic. No.: 892592-B | 2460 GLENCOE AVE VENICE, CA 90291 |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 22634 SYLVAN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/29/2024 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 1/29/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 2/1/2024 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 3/14/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 3/20/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 3/20/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 4/3/2024 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Approved | HERBERT GIRON |
| HVAC-Final | 4/3/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 4/3/2024 | Approved | HERBERT GIRON |
| Deputy Drilled-In Anchors | 4/8/2024 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/10/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 4/10/2024 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/18/2024 | Approved | HERBERT GIRON |
| Green Building Rough | 4/18/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/18/2024 | Partial Approval | HERBERT GIRON |
| Insulation | 4/22/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 4/26/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/30/2024 | Approved | HERBERT GIRON |
| Shower Pan | 4/30/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 7/3/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 7/3/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 7/9/2024 | Approved | HERBERT GIRON |
| Final | 7/9/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 7/9/2024 | Approved | HERBERT GIRON |
| HVAC-Final | 7/9/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 7/9/2024 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 7/9/2024 | Approved | HERBERT GIRON |
| Final | 7/11/2024 | OK to Issue CofO | HERBERT GIRON |