629 S SYCAMORE AVE 90036
Certificate Information: 629 S SYCAMORE AVE 90036
- Application / Permit
- 23014-30000-04961
- Plan Check / Job No.
- B23WL02974
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO AND REMODEL OF AN (E) SFD. RELOCATE KITCHEN AND LAUNDRY AREA. CREATE NEW BEDROOM AND EXPAND MASTER BEDROOM. 2 NEW BATHROOMS.
- Permit Issued
- Issued on 12/14/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2023 | RICHARD GARCIA |
| Corrections Issued | 12/8/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 12/8/2023 | APPLICANT |
| Applicant returned to address corrections | 12/11/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 12/13/2023 | CAROLEAN BASMA |
| Issued | 12/14/2023 | APPLICANT |
| CofO in Progress | 2/10/2025 | ENRIQUE MIRELES |
| CofO in Progress | 2/11/2025 | ENRIQUE MIRELES |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
| CofO Issued | 2/13/2025 | DEROLD HAUFF |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2023 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 12/8/2023 | CELINA MORENO |
| Sewer availability | Cleared | 12/8/2023 | CELINA MORENO |
| CPC | Cleared | 12/12/2023 | JASON CHAN |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/18/2024 | Conditional Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 4/19/2024 | Corrections Issued | JOSEPH MCGARRY |
| METHANE-Barrier | 4/19/2024 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 4/19/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/9/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Wood Frame | 5/9/2024 | Partial Approval | RONNIE MINDANAO |
| Insulation | 5/14/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 5/14/2024 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/16/2024 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 7/16/2024 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 7/16/2024 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2024 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 7/23/2024 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2024 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 7/23/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 8/19/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 12/5/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 12/5/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 12/5/2024 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 12/5/2024 | Approved | RONNIE MINDANAO |
| Gas Test | 12/5/2024 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 12/5/2024 | Approved | RONNIE MINDANAO |
| Green Building Rough | 12/5/2024 | Approved | RONNIE MINDANAO |
| HVAC-Final | 12/5/2024 | Approved | RONNIE MINDANAO |
| METHANE-Final | 12/5/2024 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 12/5/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 12/5/2024 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 12/5/2024 | SGSOV Approved | RONNIE MINDANAO |
| Service/Power Release | 12/5/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Smoke Detectors | 12/5/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 12/9/2024 | Approved | RONNIE MINDANAO |
| Gas Test | 12/9/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 12/9/2024 | Approved | RONNIE MINDANAO |
| Final | 12/12/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 12/31/2024 | Conditional Approval | JOSE MACIAS |
| Final | 2/6/2025 | OK to Issue CofO | ENRIQUE MIRELES |
| Final | 2/10/2025 | OK to Issue CofO | ENRIQUE MIRELES |