8324 S MCCONNELL AVE 90045
Certificate Information: 8324 S MCCONNELL AVE 90045
- Application / Permit
- 23014-30000-04860
- Plan Check / Job No.
- B23WL02919
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and addition to (E) 1-story SFD and enclose portion of (E) covered porch at front to extend (E) bedroom, add a bathroom.
- Permit Issued
- Issued on 12/29/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2023 | RICHARD GARCIA |
| Corrections Issued | 12/1/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 12/5/2023 | APPLICANT |
| Plan Check Approved | 12/29/2023 | CAROLEAN BASMA |
| Issued | 12/29/2023 | APPLICANT |
| CofO in Progress | 6/13/2024 | BOBBY KEY |
| Permit Finaled | 6/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/17/2024 | DANIEL ORRANTE |
| CofO Issued | 6/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2023 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 12/14/2023 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/4/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 1/5/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 1/10/2024 | Partial Inspection | BEN MOLSTAD |
| Underground Mechanical | 1/10/2024 | Partial Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 1/11/2024 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Partial Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 1/29/2024 | Not Ready for Inspection | BOBBY KEY |
| Special/Order Compliance | 1/29/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 1/31/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 2/12/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 2/20/2024 | Not Ready for Inspection | BOBBY KEY |
| Special/Order Compliance | 2/20/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 2/28/2024 | Conditional Approval | BOBBY KEY |
| Special/Order Compliance | 2/28/2024 | Partial Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 3/6/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 3/6/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 3/12/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 3/12/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2024 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 3/14/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 3/14/2024 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 3/18/2024 | Approved | BOBBY KEY |
| Deputy Wood Construction | 3/19/2024 | Conditional Approval | BOBBY KEY |
| Interior/Exterior Lathing | 3/21/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/27/2024 | Approved | BOBBY KEY |
| Green Building Rough | 3/27/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 3/27/2024 | Partial Approval | BOBBY KEY |
| Insulation | 4/1/2024 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 4/1/2024 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 4/1/2024 | Corrections Issued | BOBBY KEY |
| Insulation | 4/4/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 4/16/2024 | Approved | BOBBY KEY |
| Smoke Detectors | 4/16/2024 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 4/19/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 5/1/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 6/6/2024 | Partial Approval | BOBBY KEY |
| HVAC-Final | 6/6/2024 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Final | 6/13/2024 | Approved | BOBBY KEY |
| Final | 6/13/2024 | OK to Issue CofO | BOBBY KEY |
| Green Building Final | 6/13/2024 | Approved | BOBBY KEY |
| HVAC-Final | 6/13/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 6/13/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/13/2024 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 6/13/2024 | Approved | BOBBY KEY |
| Smoke Detectors | 6/13/2024 | Approved | BOBBY KEY |