13838 W RUNNYMEDE ST 91405

Certificate Information: 13838 W RUNNYMEDE ST 91405

Application / Permit
23014-30000-04740
Plan Check / Job No.
B23WL02872
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached garage to one-story ADU per LAMC 12.22A33(c )-(d) with a 21' x 14', 294 sf addition in the rear of the lot.
Permit Issued
Issued on 12/13/2023
Issuing Office
West Los Angeles
Current Status
Issued on 12/13/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/17/2023 APPLICANT
Assigned to Plan Check Engineer 11/22/2023 JAHANSHAH POURHASSAN
Corrections Issued 11/26/2023 JAHANSHAH POURHASSAN
Building Plans Picked Up 11/28/2023 APPLICANT
Plan Check Approved 12/13/2023 CAROLEAN BASMA
Issued 12/13/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/6/2023 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 12/6/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/7/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/7/2023 EDGAR ALCARAZ

Contact Information

Architect Khoudikian,, Kaaren G; Lic. No.: C13183 6906 FOOTHILL BLVD.      TUJUNGA, CA 91042
Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/31/2024 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 4/9/2024 Corrections Issued KIRK SANDERS
Deputy Drilled-In Anchors 4/22/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/29/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 5/7/2024 Approved KIRK SANDERS
PLUMBING-Rough 5/7/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 8/2/2024 Corrections Issued VINCENT HANLEY
Green Building Rough 8/2/2024 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 12/13/2024 Corrections Issued VINCENT HANLEY
Green Building Rough 12/13/2024 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 4/3/2025 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 4/3/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Approved VINCENT HANLEY
Green Building Rough 4/3/2025 Approved VINCENT HANLEY
HVAC-Rough 4/3/2025 Approved VINCENT HANLEY
PLUMBING-Rough 4/3/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/14/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 4/14/2025 Partial Inspection MISAEL ESPARZA
HVAC-Rough 4/14/2025 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 4/14/2025 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 4/23/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Approved VINCENT HANLEY
Insulation 6/5/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 6/5/2025 Approved MATTHEW NELSON
Drywall Nailing 8/27/2025 Corrections Issued DAVID MATSON
Drywall Nailing 10/20/2025 Approved MATTHEW NELSON
Underground Mechanical 10/20/2025 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 11/12/2025 Approved LOUIS ESCOTO