1444 N FOREST KNOLL DR 90069

Certificate Information: 1444 N FOREST KNOLL DR 90069

Application / Permit
23014-30000-04712
Plan Check / Job No.
B23WL02853
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Enclose balcony to add to floor area. remodel and addition to (e) S.F.D,
Permit Issued
Issued on 3/7/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2023 APPLICANT
Assigned to Plan Check Engineer 11/21/2023 YASHAR EMAMI
Corrections Issued 11/30/2023 YASHAR EMAMI
Quality Review Completed 11/30/2023 REZA HAGHIGHAT
Building Plans Picked Up 12/4/2023 APPLICANT
Applicant returned to address corrections 12/20/2023 YASHAR EMAMI
Applicant returned to address corrections 1/11/2024 YASHAR EMAMI
Plan Check Approved 3/5/2024 YASHAR EMAMI
Issued 3/7/2024 APPLICANT
CofO in Progress 6/17/2025 ROY SPAULDING
Permit Finaled 6/29/2025 DEROLD HAUFF
CofO Issued 6/29/2025 DEROLD HAUFF
Permit Finaled 6/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/26/2023 SERGIO VALENZUELA
Tract Map conditions Cleared 12/26/2023 JAZMIN ROQUE
ZA Case Cleared 12/26/2023 JAZMIN ROQUE
Roof/Waste drainage to street Cleared 1/18/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 1/24/2024 CHRISTINA BRACO
ZA Case Cleared 2/1/2024 MARC WOERSCHING
Hydrant and Access approval Cleared 2/3/2024 RUEL COLE
Private sewage disp. approval Cleared 2/22/2024 MICHAEL TEMPLE

Contact Information

Architect Scrafano,, Elissa F; Lic. No.: C26071 163 N SYCAMORE      LOS ANGELES, CA 90036
Contractor Green Works Construction & Design Inc; Lic. No.: 936962-B 20301 VENTURA BLVD #222      WOODLAND HILLS, CA 91364
Engineer Tuchscher,, James; Lic. No.: C77649 5318 E 2ND ST., #539      LONG BEACH, CA 90803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 5/15/2024 Partial Approval RICHARD DOCKUS
Deputy Drilled-In Anchors 5/29/2024 Conditional Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 6/5/2024 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 6/13/2024 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 6/13/2024 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Partial Inspection RAUL BARAJAS
Green Building Rough 6/13/2024 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 6/13/2024 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 6/13/2024 Approved RAUL BARAJAS
Shower Pan 6/13/2024 Approved RAUL BARAJAS
BUILDING-Rough-Frame 6/24/2024 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 6/24/2024 Partial Approval RAUL BARAJAS
Green Building Rough 6/24/2024 Partial Approval RAUL BARAJAS
HVAC-Rough 6/24/2024 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 6/24/2024 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 6/28/2024 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 7/1/2024 Approved JOSH MEISTER
BUILDING-Rough-Frame 7/18/2024 Conditional Approval RAUL BARAJAS
ELECTRICAL-Rough 7/18/2024 Corrections Issued RAUL BARAJAS
Green Building Rough 7/18/2024 Approved RAUL BARAJAS
HVAC-Rough 7/18/2024 Partial Approval RAUL BARAJAS
Insulation 7/31/2024 Approved JOSH MEISTER
Drywall Nailing 8/13/2024 Approved RAUL BARAJAS
ELECTRICAL-Final 1/27/2025 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 3/27/2025 Approved ROY SPAULDING
Final 3/27/2025 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 3/27/2025 Approved ROY SPAULDING
Green Building Final 3/27/2025 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 3/27/2025 Approved ROY SPAULDING
Final 4/3/2025 Corrections Issued ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Approved ROY SPAULDING
Final 6/16/2025 OK to Issue CofO ROY SPAULDING