1130 N STONE CANYON ROAD 90077
Certificate Information: 1130 N STONE CANYON ROAD 90077
- Application / Permit
- 23014-30000-04671
- Plan Check / Job No.
- B23WL02826
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- First and second floor nterior remodel and 1-story addition to the side of existing SFD.
- Permit Issued
- Issued on 12/29/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | JAHANSHAH POURHASSAN |
| Corrections Issued | 11/17/2023 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 11/21/2023 | APPLICANT |
| Plan Check Approved | 12/12/2023 | JAHANSHAH POURHASSAN |
| Issued | 12/29/2023 | APPLICANT |
| CofO in Progress | 5/22/2026 | EVAN COOPER |
| Permit Finaled | 5/27/2026 | RICHARD STEINBACH |
| CofO Issued | 5/27/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/27/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/17/2023 | JAHANSHAH POURHASSAN |
| Certificate of Compliance | Cleared | 11/29/2023 | YINGSHI HUANG |
| Roof/Waste drainage to street | Cleared | 12/4/2023 | BRENDEN HAWK |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2023 | BRENDEN HAWK |
| Miscellaneous | Cleared | 12/12/2023 | JAHANSHAH POURHASSAN |
Contact Information
| Contractor | Pacific Royal Development; Lic. No.: 1093832-B | 19226 LOS ALIMOS STREET PORTER RANCH, CA 91326 |
| Engineer | Samara,, Muzahim; Lic. No.: C26015 | 9100 S SEPULVEDA BLVD SUITE 115 LOS ANGELES, CA 90045 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/10/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/12/2024 | No Access for Inspection | STEPHANIE SWANSON |
| Gas Test | 1/17/2024 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 1/17/2024 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 1/19/2024 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 6/7/2024 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 7/2/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 7/2/2024 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/8/2024 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/14/2024 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 8/19/2024 | Corrections Issued | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 8/19/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 8/19/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 8/19/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Insulation | 8/19/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/22/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 8/22/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 8/22/2024 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 8/22/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/3/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Drywall Nailing | 11/14/2024 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 11/14/2024 | Approved | CHRISTOPHER WILSON |
| Insulation | 11/14/2024 | Approved | CHRISTOPHER WILSON |
| Pre-Inspection | 5/13/2025 | Partial Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 9/2/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Service/Power Release | 9/2/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Service/Power Release | 9/15/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 9/18/2025 | Partial Inspection | CHRISTOPHER WILSON |
| Smoke Detectors | 2/9/2026 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 5/4/2026 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 5/4/2026 | Approved | EVAN COOPER |
| Final | 5/4/2026 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 5/4/2026 | Approved | EVAN COOPER |
| Green Building Final | 5/4/2026 | Approved | EVAN COOPER |
| HVAC-Final | 5/4/2026 | Approved | EVAN COOPER |
| PLUMBING-Final | 5/4/2026 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/4/2026 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 5/4/2026 | Approved | EVAN COOPER |
| Final | 5/13/2026 | Corrections Issued | RYAN SALAZAR |
| Final | 5/22/2026 | OK to Issue CofO | EVAN COOPER |