4954-4956 N REFORMA ROAD 91364
Certificate Information: 4954-4956 N REFORMA ROAD 91364
- Application / Permit
- 23014-30000-04573
- Plan Check / Job No.
- B23WL02785
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Alteration and addition to an (e) S.F.D. 950 sf addition and interior remodel and converesion existing garage to an JADU
- Permit Issued
- Issued on 5/6/2024
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 11/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | HOOMAN HAJIZADEH |
| Corrections Issued | 12/1/2023 | HOOMAN HAJIZADEH |
| Quality Review Completed | 12/7/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 12/7/2023 | APPLICANT |
| Applicant returned to address corrections | 1/10/2024 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 2/2/2024 | HOOMAN HAJIZADEH |
| Plan Check Approved | 2/28/2024 | HOOMAN HAJIZADEH |
| Issued | 5/6/2024 | APPLICANT |
| CofO in Progress | 11/14/2025 | JOHN HAYES |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 11/30/2023 | HOOMAN HAJIZADEH |
| Grading Pre-Inspection | Cleared | 11/30/2023 | HOOMAN HAJIZADEH |
| BHO/Hillside ordinance | Cleared | 12/15/2023 | NIKKI ZULUETA |
| BHO/Hillside ordinance | Cleared | 12/15/2023 | NIKKI ZULUETA |
| BHO/Hillside ordinance | Cleared | 12/15/2023 | NIKKI ZULUETA |
| BHO/Hillside ordinance | Cleared | 12/15/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 1/10/2024 | ROGELIO CORTES |
| BHO/Hillside ordinance | Cleared | 1/11/2024 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 1/17/2024 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2024 | NIKKI ZULUETA |
| Sewer availability | Cleared | 1/24/2024 | NIKKI ZULUETA |
| Address approval | Cleared | 1/25/2024 | NIKKI ZULUETA |
| Hydrant and Access approval | Cleared | 1/29/2024 | GILBERT URREA |
Contact Information
| Contractor | Moalem Corporation; Lic. No.: 1061118-B | 8610 CHALMERS DR 203 LOS ANGELES, CA 90035 |
| Engineer | Azarmy,, Cyrus; Lic. No.: L9404 | 4402 CHARLEMONT AVE WOODLAND HILLS, CA 91364 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/21/2024 | Conditional Approval | JOHN HAYES |
| PLUMBING-Rough | 6/28/2024 | Partial Approval | JOHN HAYES |
| Sewer | 6/28/2024 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/2/2024 | Not Ready for Inspection | HENRY KIM |
| Footing/Foundation/Slab | 7/2/2024 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 7/9/2024 | Corrections Issued | JOHN HAYES |
| Deputy Drilled-In Anchors | 7/10/2024 | No Access for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/10/2024 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/12/2024 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 7/12/2024 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/16/2024 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 7/16/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 7/19/2024 | Partial Inspection | SEAN WIRCH |
| Footing/Foundation/Slab | 7/19/2024 | Partial Approval | MORRIS JACKSON |
| Special/Order Compliance | 7/19/2024 | Corrections Issued | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 8/1/2024 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 8/1/2024 | Approved | JOHN HAYES |
| Insulation | 10/8/2024 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 11/7/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 11/19/2024 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 11/19/2024 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 1/6/2025 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Partial Approval | JOHN HAYES |
| Green Building Rough | 1/6/2025 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 1/6/2025 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 1/17/2025 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Approved | JOHN HAYES |
| Green Building Rough | 1/17/2025 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 1/17/2025 | Approved | JOHN HAYES |
| Wood Frame | 1/17/2025 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 2/7/2025 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 2/11/2025 | Partial Approval | JOHN HAYES |
| Insulation | 2/20/2025 | Approved | JOHN COLEMAN |
| ELECTRICAL-Rough | 3/11/2025 | Approved | JOHN COLEMAN |
| Drywall Nailing | 3/24/2025 | Approved | JOHN COLEMAN |
| Shower Pan | 4/14/2025 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 4/28/2025 | Approved | SCOTT SOBEL |
| Final | 9/22/2025 | Corrections Issued | JOHN HAYES |
| Green Building Final | 9/22/2025 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/22/2025 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 9/22/2025 | Approved | JOHN HAYES |
| Final | 11/7/2025 | Corrections Issued | JOHN HAYES |
| Final | 11/14/2025 | OK to Issue CofO | JOHN HAYES |