8402 S LOYOLA BLVD 90045

Certificate Information: 8402 S LOYOLA BLVD 90045

Application / Permit
23014-30000-04559
Plan Check / Job No.
B23WL02778
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERSION OF A 2-STORY DETACHED GARAGE/REC ROOM INTO AN ADU BY ADDING STAIRS AND KITCHEN PLUS 1/2 BATH DOWNSTAIRS WITH 2 BEDROOMS AND FULL BATH UPSTAIRS. CONVERSION BY LAMC 12.22 A.33(c)-(d)
Permit Issued
Issued on 1/5/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2023 APPLICANT
Assigned to Plan Check Engineer 11/13/2023 RICHARD GARCIA
Corrections Issued 11/13/2023 RICHARD GARCIA
Applicant returned to address corrections 12/8/2023 AMY GUEVARRA
Plan Check Approved 1/5/2024 CAROLEAN BASMA
Issued 1/5/2024 APPLICANT
CofO in Progress 8/12/2024 BOBBY KEY
Permit Finaled 8/13/2024 RICHARD STEINBACH
CofO Issued 8/13/2024 RICHARD STEINBACH
Permit Finaled 8/13/2024 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 1/2/2024 FREDDY GARCIA
Address approval Cleared 1/3/2024 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/4/2024 DINAH GARIN
Roof/Waste drainage to street Cleared 1/4/2024 BRENDEN HAWK
Sewer availability Cleared 1/4/2024 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Paniagua,, Cristobal; Lic. No.: C72894 1538 W 92ND ST      LOS ANGELES, CA 90047

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/11/2024 Conditional Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 1/16/2024 Approved BOBBY KEY
Footing/Foundation/Slab 1/16/2024 Approved BOBBY KEY
PLUMBING-Rough 1/16/2024 Partial Approval BOBBY KEY
ELECTRICAL-Rough 3/4/2024 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Corrections Issued BOBBY KEY
HVAC-Rough 3/4/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 3/4/2024 Not Ready for Inspection BOBBY KEY
Underground Mechanical 3/4/2024 Corrections Issued BOBBY KEY
Deputy Wood Construction 3/7/2024 Conditional Approval TEMISTOCLES CAAL
Deputy Wood Construction 3/11/2024 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 3/14/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/14/2024 Partial Approval BOBBY KEY
Green Building Rough 3/14/2024 Not Ready for Inspection BOBBY KEY
HVAC-Rough 3/14/2024 Corrections Issued BOBBY KEY
PLUMBING-Rough 3/14/2024 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 4/2/2024 Conditional Approval BOBBY KEY
Green Building Rough 4/2/2024 Approved BOBBY KEY
HVAC-Rough 4/2/2024 Approved BOBBY KEY
Interior/Exterior Lathing 4/2/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 4/2/2024 Approved BOBBY KEY
Insulation 4/4/2024 Corrections Issued BOBBY KEY
Insulation 4/8/2024 Approved BOBBY KEY
Deputy Wood Construction 4/10/2024 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 4/11/2024 Approved BOBBY KEY
Drywall Nailing 4/18/2024 Approved RICHARD STEINBACH
ELECTRICAL-Final 6/14/2024 Corrections Issued HERBERT GIRON
Final 6/14/2024 Corrections Issued HERBERT GIRON
Green Building Final 6/14/2024 Corrections Issued HERBERT GIRON
HVAC-Final 6/14/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 6/14/2024 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 6/14/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 6/14/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 7/30/2024 Corrections Issued HERBERT GIRON
Final 7/30/2024 Corrections Issued HERBERT GIRON
Green Building Final 7/30/2024 Not Ready for Inspection HERBERT GIRON
HVAC-Final 7/30/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 7/30/2024 Corrections Issued HERBERT GIRON
Smoke Detectors 7/30/2024 Approved HERBERT GIRON
ELECTRICAL-Final 8/5/2024 Approved BOBBY KEY
Final 8/5/2024 Not Ready for Inspection BOBBY KEY
Gas Test 8/5/2024 Not Ready for Inspection BOBBY KEY
Green Building Final 8/5/2024 Approved BOBBY KEY
HVAC-Final 8/5/2024 Not Ready for Inspection BOBBY KEY
PLUMBING-Final 8/5/2024 Not Ready for Inspection BOBBY KEY
Final 8/7/2024 OK to Issue CofO BOBBY KEY
Gas Test 8/7/2024 Approved BOBBY KEY
HVAC-Final 8/7/2024 Approved BOBBY KEY
PLUMBING-Final 8/7/2024 Approved BOBBY KEY