8402 S LOYOLA BLVD 90045
Certificate Information: 8402 S LOYOLA BLVD 90045
- Application / Permit
- 23014-30000-04559
- Plan Check / Job No.
- B23WL02778
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERSION OF A 2-STORY DETACHED GARAGE/REC ROOM INTO AN ADU BY ADDING STAIRS AND KITCHEN PLUS 1/2 BATH DOWNSTAIRS WITH 2 BEDROOMS AND FULL BATH UPSTAIRS. CONVERSION BY LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 1/5/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2023 | RICHARD GARCIA |
| Corrections Issued | 11/13/2023 | RICHARD GARCIA |
| Applicant returned to address corrections | 12/8/2023 | AMY GUEVARRA |
| Plan Check Approved | 1/5/2024 | CAROLEAN BASMA |
| Issued | 1/5/2024 | APPLICANT |
| CofO in Progress | 8/12/2024 | BOBBY KEY |
| Permit Finaled | 8/13/2024 | RICHARD STEINBACH |
| CofO Issued | 8/13/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/13/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/2/2024 | FREDDY GARCIA |
| Address approval | Cleared | 1/3/2024 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2024 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 1/4/2024 | BRENDEN HAWK |
| Sewer availability | Cleared | 1/4/2024 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Paniagua,, Cristobal; Lic. No.: C72894 | 1538 W 92ND ST LOS ANGELES, CA 90047 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/11/2024 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 1/16/2024 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 1/16/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 1/16/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 3/4/2024 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 3/4/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 3/4/2024 | Not Ready for Inspection | BOBBY KEY |
| Underground Mechanical | 3/4/2024 | Corrections Issued | BOBBY KEY |
| Deputy Wood Construction | 3/7/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 3/11/2024 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 3/14/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2024 | Partial Approval | BOBBY KEY |
| Green Building Rough | 3/14/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 3/14/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 3/14/2024 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 4/2/2024 | Conditional Approval | BOBBY KEY |
| Green Building Rough | 4/2/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 4/2/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/2/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 4/2/2024 | Approved | BOBBY KEY |
| Insulation | 4/4/2024 | Corrections Issued | BOBBY KEY |
| Insulation | 4/8/2024 | Approved | BOBBY KEY |
| Deputy Wood Construction | 4/10/2024 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 4/11/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 4/18/2024 | Approved | RICHARD STEINBACH |
| ELECTRICAL-Final | 6/14/2024 | Corrections Issued | HERBERT GIRON |
| Final | 6/14/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 6/14/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 6/14/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 6/14/2024 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/14/2024 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 6/14/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 7/30/2024 | Corrections Issued | HERBERT GIRON |
| Final | 7/30/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 7/30/2024 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 7/30/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 7/30/2024 | Corrections Issued | HERBERT GIRON |
| Smoke Detectors | 7/30/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 8/5/2024 | Approved | BOBBY KEY |
| Final | 8/5/2024 | Not Ready for Inspection | BOBBY KEY |
| Gas Test | 8/5/2024 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 8/5/2024 | Approved | BOBBY KEY |
| HVAC-Final | 8/5/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 8/5/2024 | Not Ready for Inspection | BOBBY KEY |
| Final | 8/7/2024 | OK to Issue CofO | BOBBY KEY |
| Gas Test | 8/7/2024 | Approved | BOBBY KEY |
| HVAC-Final | 8/7/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 8/7/2024 | Approved | BOBBY KEY |