1146 N MAYBROOK DR 90210
Certificate Information: 1146 N MAYBROOK DR 90210
- Application / Permit
- 23014-30000-04371
- Plan Check / Job No.
- B23WL02672
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO AND COMPLETE REMODEL OF AN (E) SFD. NEW INTERIOR PARTITIONS, NEW FLAT ROOF STRUCTURE, NEW DOORS AND WINDOWS, NEW EXTERIOR STUCCO REPAIRS...
- Permit Issued
- Issued on 1/31/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2023 | RICHARD GARCIA |
| Corrections Issued | 10/25/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 10/26/2023 | APPLICANT |
| Plan Check Approved | 11/17/2023 | DAVID CASTILLO |
| Issued | 1/31/2024 | APPLICANT |
| CofO in Progress | 12/4/2025 | SEAN HAUPT |
| Permit Finaled | 12/6/2025 | RICHARD STEINBACH |
| CofO Issued | 12/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/27/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2023 | DARIN LAM |
| Sewer availability | Cleared | 10/28/2023 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 11/14/2023 | SERGIO VALENZUELA |
Contact Information
| Contractor | Lightning Construction & Design Inc; Lic. No.: 951122-B | 6047 TAMPA AVE #303 TARZANA, CA 91356 |
| Engineer | Perazzelli,, Joseph Ames; Lic. No.: C35270 | 183 GREENFIELD AVENUE LOS ANGELES, CA 90049 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/26/2024 | Conditional Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 3/7/2024 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 4/15/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 5/17/2024 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 5/17/2024 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 8/7/2024 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Approved | SEAN HAUPT |
| HVAC-Rough | 8/9/2024 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 8/9/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 8/13/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 8/13/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 8/13/2024 | Approved | SEAN HAUPT |
| HVAC-Rough | 8/13/2024 | Approved | SEAN HAUPT |
| Insulation | 9/11/2024 | Approved | SEAN HAUPT |
| Shower Pan | 9/11/2024 | Approved | SEAN HAUPT |
| Drywall Nailing | 9/18/2024 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 9/18/2024 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 5/20/2025 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 8/29/2025 | Approved | MEL KHACHATOURIAN |
| Service/Power Release | 8/29/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 9/17/2025 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Final | 9/17/2025 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 9/17/2025 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 9/17/2025 | Not Ready for Inspection | SEAN HAUPT |
| Final | 9/19/2025 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 9/19/2025 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 9/19/2025 | Approved | SEAN HAUPT |
| Service/Power Release | 9/30/2025 | Approved | SEAN HAUPT |
| Final | 11/20/2025 | Partial Approval | SEAN HAUPT |
| Green Building Final | 11/20/2025 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Approved | SEAN HAUPT |
| Final | 12/3/2025 | OK to Issue CofO | SEAN HAUPT |