10508 W DUNLEER DR 90064
Certificate Information: 10508 W DUNLEER DR 90064
- Application / Permit
- 23014-30000-04354
- Plan Check / Job No.
- B23WL02667
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING. 1ST AND 2ND FLOOR ADDITION, BASEMENT ADDITION, AND ATTACHED GARAGE IN BASEMENT, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 2/9/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2023 | SERGIO SILVA |
| Corrections Issued | 11/3/2023 | SERGIO SILVA |
| Quality Review Completed | 11/12/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 11/14/2023 | APPLICANT |
| Plan Check Approved | 1/3/2024 | SERGIO SILVA |
| Issued | 2/9/2024 | APPLICANT |
| CofO in Progress | 4/9/2026 | ASHLEY THOMPSON |
| Permit Finaled | 4/9/2026 | RICHARD STEINBACH |
| CofO Issued | 4/9/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/9/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 11/3/2023 | MAXFIELD VERMY |
| ZA Case | Cleared | 11/3/2023 | MAXFIELD VERMY |
| Permit | Cleared | 11/6/2023 | ANDREA SAINT-ANTONIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2023 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 11/28/2023 | ANDREA SAINT-ANTONIN |
| Low Impact Development (LID) | Cleared | 12/7/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 12/7/2023 | ANDREA SAINT-ANTONIN |
| Specific Plan | Cleared | 12/14/2023 | FREDDY GARCIA |
| Trees in Parkway | Cleared | 12/14/2023 | ADALBERTO VERA |
| Excavation more than 5-ft deep | Cleared | 1/3/2024 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 1/3/2024 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 1/3/2024 | SERGIO SILVA |
| Miscellaneous | Cleared | 1/3/2024 | SERGIO SILVA |
| Miscellaneous | Cleared | 1/3/2024 | SERGIO SILVA |
| Miscellaneous | Cleared | 1/3/2024 | SERGIO SILVA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Bookie Development Inc; Lic. No.: 977585-B | 10509 CLARKSON ROAD LOS ANGELES, CA 90064 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Ganeshwara,, Vela; Lic. No.: GE2736 | 19420 KILFINAN ST PORTER RANCH, CA 91326 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/12/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Piling/Pier/Caisson | 5/9/2024 | Corrections Issued | MICHAEL PELHAM |
| Footing/Foundation/Slab | 5/28/2024 | Partial Approval | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 6/13/2024 | Partial Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 7/17/2024 | Partial Approval | SEAN HAUPT |
| Underground Mechanical | 7/23/2024 | Corrections Issued | KIRK SANDERS |
| Sewer | 7/25/2024 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 7/25/2024 | Partial Approval | REGINA MENDEZ |
| PLUMBING-Rough | 9/9/2024 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/1/2024 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 10/10/2024 | Approved | ASHLEY THOMPSON |
| Deputy Wood Construction | 11/5/2024 | Conditional Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2024 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Wood Construction | 12/18/2024 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Corrections Issued | KIRK SANDERS |
| Verify Sprinkler Sign Off | 12/18/2024 | Not Ready for Inspection | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Partial Approval | STEPHANIE SWANSON |
| Green Building Rough | 1/30/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/11/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 4/17/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 4/18/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 4/22/2025 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/1/2025 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 5/1/2025 | Approved | STEPHANIE SWANSON |
| Insulation | 6/6/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Special/Order Compliance | 6/6/2025 | Partial Inspection | HERBERT GIRON |
| Deputy Wood Construction | 6/12/2025 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 6/18/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 6/18/2025 | Approved | TEMISTOCLES CAAL |
| Insulation | 6/18/2025 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 6/18/2025 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 7/7/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/5/2025 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 8/5/2025 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 12/8/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 1/7/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 1/8/2026 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Final | 1/12/2026 | Corrections Issued | ASHLEY THOMPSON |
| Gas Test | 1/14/2026 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 1/14/2026 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2026 | SGSOV Approved | ARAM AVEDISIAN |
| Gas Test | 1/23/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 1/23/2026 | Approved | ASHLEY THOMPSON |
| Final | 3/12/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Final | 3/12/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Reinforced Concrete Frame | 3/12/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Smoke Detectors | 3/12/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 3/24/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 3/24/2026 | Approved | ASHLEY THOMPSON |
| Reinforced Concrete Frame | 3/24/2026 | Approved | ASHLEY THOMPSON |
| Smoke Detectors | 3/24/2026 | Approved | ASHLEY THOMPSON |
| Final | 3/31/2026 | Partial Approval | ASHLEY THOMPSON |
| Final | 4/7/2026 | OK to Issue CofO | ASHLEY THOMPSON |