2307 S LOUELLA AVE 90291

Certificate Information: 2307 S LOUELLA AVE 90291

Application / Permit
23014-30000-04282
Plan Check / Job No.
B23WL02616
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and 2nd story addition to existing SFD by keeping portion of foundation and wall
Permit Issued
Issued on 1/23/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2023 APPLICANT
Assigned to Plan Check Engineer 10/26/2023 HOOMAN HAJIZADEH
Corrections Issued 10/30/2023 HOOMAN HAJIZADEH
Quality Review Completed 11/6/2023 KAVIAN REFAHI
Building Plans Picked Up 11/7/2023 APPLICANT
Plan Check Approved 12/20/2023 HOOMAN HAJIZADEH
Issued 1/23/2024 APPLICANT
CofO in Progress 4/9/2025 JESUS RODRIGUEZ
Permit Finaled 4/21/2025 RICHARD STEINBACH
CofO Issued 4/21/2025 RICHARD STEINBACH
Permit Finaled 4/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/31/2023 ANDREA SAINT-ANTONIN
Permit Cleared 10/31/2023 ANDREA SAINT-ANTONIN
Sewer availability Cleared 10/31/2023 ANDREA SAINT-ANTONIN
Low Impact Development (LID) Cleared 11/7/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 11/7/2023 ANDREA SAINT-ANTONIN

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/12/2024 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 3/21/2024 Approved HERBERT GIRON
Footing/Foundation/Slab 3/21/2024 Approved HERBERT GIRON
Deputy Wood Construction 4/9/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/9/2024 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 4/10/2024 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Partial Approval HERBERT GIRON
Sewer 6/10/2024 Approved HERBERT GIRON
Underground Mechanical 6/10/2024 Approved HERBERT GIRON
ELECTRICAL-Rough 6/14/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 6/14/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 6/18/2024 Approved HERBERT GIRON
HVAC-Rough 6/18/2024 Approved HERBERT GIRON
Shower Pan 6/18/2024 Approved HERBERT GIRON
PLUMBING-Rough 6/27/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 8/15/2024 Corrections Issued HERBERT GIRON
Green Building Rough 8/15/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 8/15/2024 Partial Approval HERBERT GIRON
PLUMBING-Final 8/15/2024 Approved HERBERT GIRON
Verify Sprinkler Sign Off 8/15/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 8/19/2024 Approved TEMISTOCLES CAAL
Insulation 8/19/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 8/19/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 8/26/2024 Approved ARAM AVEDISIAN
Gas Test 2/5/2025 Not Ready for Inspection HERBERT GIRON
Gas Test 2/6/2025 Approved HERBERT GIRON
ELECTRICAL-Final 3/6/2025 Conditional Approval TEMISTOCLES CAAL
HVAC-Final 3/6/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 4/9/2025 Approved JESUS RODRIGUEZ
Final 4/9/2025 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 4/9/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/9/2025 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 4/9/2025 Approved JESUS RODRIGUEZ