2307 S LOUELLA AVE 90291
Certificate Information: 2307 S LOUELLA AVE 90291
- Application / Permit
- 23014-30000-04282
- Plan Check / Job No.
- B23WL02616
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2nd story addition to existing SFD by keeping portion of foundation and wall
- Permit Issued
- Issued on 1/23/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/26/2023 | HOOMAN HAJIZADEH |
| Corrections Issued | 10/30/2023 | HOOMAN HAJIZADEH |
| Quality Review Completed | 11/6/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 11/7/2023 | APPLICANT |
| Plan Check Approved | 12/20/2023 | HOOMAN HAJIZADEH |
| Issued | 1/23/2024 | APPLICANT |
| CofO in Progress | 4/9/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
| CofO Issued | 4/21/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/21/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2023 | ANDREA SAINT-ANTONIN |
| Permit | Cleared | 10/31/2023 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 10/31/2023 | ANDREA SAINT-ANTONIN |
| Low Impact Development (LID) | Cleared | 11/7/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 11/7/2023 | ANDREA SAINT-ANTONIN |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/12/2024 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 3/21/2024 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 3/21/2024 | Approved | HERBERT GIRON |
| Deputy Wood Construction | 4/9/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 4/10/2024 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2024 | Partial Approval | HERBERT GIRON |
| Sewer | 6/10/2024 | Approved | HERBERT GIRON |
| Underground Mechanical | 6/10/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 6/14/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 6/14/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 6/18/2024 | Approved | HERBERT GIRON |
| HVAC-Rough | 6/18/2024 | Approved | HERBERT GIRON |
| Shower Pan | 6/18/2024 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 6/27/2024 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/15/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 8/15/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 8/15/2024 | Partial Approval | HERBERT GIRON |
| PLUMBING-Final | 8/15/2024 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 8/15/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/19/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 8/19/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/19/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 8/26/2024 | Approved | ARAM AVEDISIAN |
| Gas Test | 2/5/2025 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 2/6/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 3/6/2025 | Conditional Approval | TEMISTOCLES CAAL |
| HVAC-Final | 3/6/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/9/2025 | Approved | JESUS RODRIGUEZ |
| Final | 4/9/2025 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 4/9/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/9/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 4/9/2025 | Approved | JESUS RODRIGUEZ |