4037 N CONTERA ROAD 91436
Certificate Information: 4037 N CONTERA ROAD 91436
- Application / Permit
- 23014-30000-04138
- Plan Check / Job No.
- B23WL02552
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL OF (E) SFD. PER ENGINEERING DESIGN.
- Permit Issued
- Issued on 11/16/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 11/16/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2023 | ALFREDO JARA |
| Corrections Issued | 10/15/2023 | ALFREDO JARA |
| Building Plans Picked Up | 10/17/2023 | APPLICANT |
| Applicant returned to address corrections | 10/31/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 11/3/2023 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 11/7/2023 | ALFREDO JARA |
| Issued | 11/16/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2023 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 10/31/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/1/2023 | EDGAR ALCARAZ |
| Grading Pre-Inspection | Cleared | 11/7/2023 | ALFREDO JARA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/4/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 12/12/2023 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 12/20/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 12/20/2023 | Approved | VINCENT HANLEY |
| Sewer | 12/20/2023 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 2/7/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/14/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/14/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 2/14/2024 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 2/14/2024 | Partial Approval | VINCENT HANLEY |
| Structural Steel Frame | 2/14/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/16/2024 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 2/16/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 2/28/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/6/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 3/6/2024 | Corrections Issued | VINCENT HANLEY |
| Pre-Inspection | 3/8/2024 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 3/20/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 3/20/2024 | Approved | VINCENT HANLEY |
| Insulation | 3/20/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/20/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/10/2024 | Approved | HENRY KIM |
| Sewer | 6/5/2024 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 8/6/2024 | Approved | THOMAS FINNILA |
| HVAC-Final | 8/6/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 8/6/2024 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/19/2024 | Approved | THOMAS FINNILA |
| Final | 9/19/2024 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 9/19/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 9/19/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/19/2024 | No Access for Inspection | THOMAS FINNILA |
| Smoke Detectors | 9/19/2024 | Approved | THOMAS FINNILA |