233 W 118TH ST 90061
Certificate Information: 233 W 118TH ST 90061
- Application / Permit
- 23014-30000-04096
- Plan Check / Job No.
- B23WL02539
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to existing S.F.D. Work per WFPP.
- Permit Issued
- Issued on 1/5/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2023 | RICHARD GARCIA |
| Corrections Issued | 10/13/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 10/20/2023 | APPLICANT |
| Applicant returned to address corrections | 12/21/2023 | CAROLEAN BASMA |
| Plan Check Approved | 1/3/2024 | CAROLEAN BASMA |
| Issued | 1/5/2024 | APPLICANT |
| CofO in Progress | 9/5/2024 | BARRY HACHE |
| CofO Issued | 9/11/2024 | ANSON MAGLASANG |
| Permit Finaled | 9/11/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/11/2023 | DAVID LOPEZ |
| Sewer availability | Cleared | 12/28/2023 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/2/2024 | DARIN LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/26/2024 | Corrections Issued | JAMES CHAVEZ |
| Pre-Inspection | 1/31/2024 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 2/15/2024 | Corrections Issued | JAMES CHAVEZ |
| Insulation | 2/22/2024 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 2/22/2024 | Partial Approval | JAMES CHAVEZ |
| Sewer | 2/22/2024 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 3/14/2024 | Partial Approval | BEN MOLSTAD |
| BUILDING-Rough-Frame | 4/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/11/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Rough | 4/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Rough | 4/11/2024 | Corrections Issued | BEN MOLSTAD |
| Interior/Exterior Lathing | 4/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Rough | 4/11/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 4/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 4/16/2024 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 4/16/2024 | Approved | JAMES CHAVEZ |
| Green Building Rough | 4/16/2024 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 4/16/2024 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 4/16/2024 | Partial Approval | JAMES CHAVEZ |
| PLUMBING-Rough | 4/16/2024 | Approved | JAMES CHAVEZ |
| Insulation | 4/22/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 5/10/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 5/10/2024 | Approved | BEN MOLSTAD |
| Final | 8/9/2024 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 8/9/2024 | Approved | BEN MOLSTAD |
| Green Building Final | 8/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Final | 8/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 8/9/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 8/9/2024 | Approved | BEN MOLSTAD |
| Final | 8/30/2024 | Corrections Issued | BARRY HACHE |
| Green Building Final | 8/30/2024 | Approved | BARRY HACHE |
| MERV13>=Final | 8/30/2024 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Not Ready | BARRY HACHE |
| Special/Order Compliance | 8/30/2024 | Partial Inspection | ANSON MAGLASANG |
| Final | 9/5/2024 | OK to Issue CofO | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 9/5/2024 | SGSOV Approved | BARRY HACHE |