8436 W ALLENWOOD ROAD 90046
Certificate Information: 8436 W ALLENWOOD ROAD 90046
- Application / Permit
- 23014-30000-04072
- Plan Check / Job No.
- B23WL02520
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Two (N) attached covered patios at rear of (E) S.F.D.
- Permit Issued
- Issued on 1/5/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2023 | JAHANSHAH POURHASSAN |
| Corrections Issued | 10/10/2023 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 10/19/2023 | APPLICANT |
| Plan Check Approved | 11/7/2023 | CAROLEAN BASMA |
| Issued | 1/5/2024 | APPLICANT |
| CofO in Progress | 5/18/2024 | RAUL BARAJAS |
| Permit Finaled | 5/21/2024 | RONALD MYRICK |
| CofO Issued | 5/21/2024 | RONALD MYRICK |
| Permit Finaled | 5/21/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/30/2023 | ANDREA SAINT-ANTONIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2023 | ANDREA SAINT-ANTONIN |
| Specific Plan | Cleared | 10/31/2023 | OLGA AYALA |
| Grading Pre-Inspection | Cleared | 11/7/2023 | JAHANSHAH POURHASSAN |
Contact Information
| Contractor | Axe Construction Inc; Lic. No.: 1069232-B | 6363 WILSHIRE BLVD SUITE 400 LOS ANGELES, CA 90048 |
| Engineer | Yoon,, Philip; Lic. No.: C94664 | 1221 W 3RD ST APT 234 LOS ANGELES, CA 90017 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/12/2024 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 1/12/2024 | Approved | RAUL BARAJAS |
| Green Building Rough | 1/12/2024 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 1/22/2024 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 1/22/2024 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/6/2024 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 3/6/2024 | Approved | RAUL BARAJAS |
| Green Building Rough | 3/6/2024 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 3/6/2024 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/20/2024 | Corrections Issued | RAUL BARAJAS |
| Drywall Nailing | 3/20/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 4/17/2024 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 5/9/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 5/9/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 5/9/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 5/9/2024 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 5/9/2024 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/9/2024 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 5/9/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 5/15/2024 | Corrections Issued | RAUL BARAJAS |
| Final | 5/15/2024 | No Access for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 5/15/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 5/17/2024 | Approved | RAUL BARAJAS |
| Final | 5/17/2024 | OK to Issue CofO | RAUL BARAJAS |