8436 W ALLENWOOD ROAD 90046

Certificate Information: 8436 W ALLENWOOD ROAD 90046

Application / Permit
23014-30000-04072
Plan Check / Job No.
B23WL02520
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Two (N) attached covered patios at rear of (E) S.F.D.
Permit Issued
Issued on 1/5/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2023 APPLICANT
Assigned to Plan Check Engineer 10/8/2023 JAHANSHAH POURHASSAN
Corrections Issued 10/10/2023 JAHANSHAH POURHASSAN
Building Plans Picked Up 10/19/2023 APPLICANT
Plan Check Approved 11/7/2023 CAROLEAN BASMA
Issued 1/5/2024 APPLICANT
CofO in Progress 5/18/2024 RAUL BARAJAS
Permit Finaled 5/21/2024 RONALD MYRICK
CofO Issued 5/21/2024 RONALD MYRICK
Permit Finaled 5/21/2024 RONALD MYRICK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/30/2023 ANDREA SAINT-ANTONIN
Eng Process Fee Ord 176,300 Cleared 10/31/2023 ANDREA SAINT-ANTONIN
Specific Plan Cleared 10/31/2023 OLGA AYALA
Grading Pre-Inspection Cleared 11/7/2023 JAHANSHAH POURHASSAN

Contact Information

Contractor Axe Construction Inc; Lic. No.: 1069232-B 6363 WILSHIRE BLVD SUITE 400      LOS ANGELES, CA 90048
Engineer Yoon,, Philip; Lic. No.: C94664 1221 W 3RD ST   APT 234    LOS ANGELES, CA 90017

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/12/2024 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 1/12/2024 Approved RAUL BARAJAS
Green Building Rough 1/12/2024 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 1/22/2024 Partial Approval RAUL BARAJAS
PLUMBING-Rough 1/22/2024 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 3/6/2024 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 3/6/2024 Approved RAUL BARAJAS
Green Building Rough 3/6/2024 Approved RAUL BARAJAS
PLUMBING-Final 3/6/2024 Approved RAUL BARAJAS
BUILDING-Rough-Frame 3/20/2024 Corrections Issued RAUL BARAJAS
Drywall Nailing 3/20/2024 Approved RAUL BARAJAS
Interior/Exterior Lathing 4/17/2024 Approved RAUL BARAJAS
BUILDING-Rough-Frame 5/9/2024 Approved RAUL BARAJAS
ELECTRICAL-Final 5/9/2024 Not Ready for Inspection RAUL BARAJAS
Final 5/9/2024 Not Ready for Inspection RAUL BARAJAS
Green Building Final 5/9/2024 Approved RAUL BARAJAS
PLUMBING-Final 5/9/2024 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 5/9/2024 SGSOV Approved RAUL BARAJAS
Smoke Detectors 5/9/2024 Approved RAUL BARAJAS
ELECTRICAL-Final 5/15/2024 Corrections Issued RAUL BARAJAS
Final 5/15/2024 No Access for Inspection RAUL BARAJAS
PLUMBING-Final 5/15/2024 Approved RAUL BARAJAS
ELECTRICAL-Final 5/17/2024 Approved RAUL BARAJAS
Final 5/17/2024 OK to Issue CofO RAUL BARAJAS