3555 S BENTLEY AVE 90034

Certificate Information: 3555 S BENTLEY AVE 90034

Application / Permit
23014-30000-04060
Plan Check / Job No.
B23WL02508
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story addition to (e) single story SFD and add an attached 2-car garage at the front
Permit Issued
Issued on 11/2/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 REZA HAGHIGHAT
Corrections Issued 10/14/2023 REZA HAGHIGHAT
Quality Review Completed 10/17/2023 KAVIAN REFAHI
Building Plans Picked Up 10/18/2023 APPLICANT
Plan Check Approved 11/2/2023 REZA HAGHIGHAT
Issued 11/2/2023 APPLICANT
CofO in Progress 10/30/2024 DANIEL VERA
Permit Finaled 11/5/2024 RICHARD STEINBACH
CofO Issued 11/5/2024 RICHARD STEINBACH
Permit Finaled 11/5/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/16/2023 ANDREA SAINT-ANTONIN
Sewer availability Cleared 10/16/2023 ANDREA SAINT-ANTONIN
Low Impact Development (LID) Cleared 10/31/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 10/31/2023 ANDREA SAINT-ANTONIN
GPI Written Notices Cleared 11/2/2023 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 11/2/2023 REZA HAGHIGHAT

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/15/2023 Partial Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 1/2/2024 Corrections Issued JESUS PINEDA
Excavation/Setback/Form/Re-Bar 1/8/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Partial Approval JESUS PINEDA
PLUMBING-Rough 1/29/2024 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 4/2/2024 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Rough 4/11/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 4/11/2024 Partial Approval JESUS PINEDA
PLUMBING-Rough 4/11/2024 Approved JESUS PINEDA
Shower Pan 4/11/2024 Approved JESUS PINEDA
HVAC-Rough 4/15/2024 Corrections Issued JESUS PINEDA
HVAC-Rough 4/16/2024 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 4/19/2024 Corrections Issued JESUS PINEDA
Green Building Rough 4/19/2024 Approved JESUS PINEDA
HVAC-Rough 4/19/2024 Approved JESUS PINEDA
MERV13>=Rough 4/19/2024 Approved JESUS PINEDA
Verify Sprinkler Sign Off 4/19/2024 Approved JESUS PINEDA
Wood Frame 4/19/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 4/26/2024 Approved JESUS PINEDA
Insulation 4/26/2024 Approved JESUS PINEDA
Drywall Nailing 5/1/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 5/1/2024 Partial Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 5/3/2024 Partial Inspection JESUS PINEDA
Interior/Exterior Lathing 5/28/2024 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 6/4/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 8/13/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 8/20/2024 Approved JESUS PINEDA
Service/Power Release 8/20/2024 Approved JESUS PINEDA
Final 9/26/2024 Not Ready for Inspection DANIEL VERA
Footing/Foundation/Slab 9/26/2024 Not Ready for Inspection DANIEL VERA
Green Building Final 9/26/2024 Not Ready for Inspection DANIEL VERA
MERV13>=Final 9/26/2024 Not Ready for Inspection DANIEL VERA
SGSOV-Seismic Gas S/O Valve 9/26/2024 SGSOV Not Ready DANIEL VERA
Smoke Detectors 9/26/2024 Not Ready for Inspection DANIEL VERA
HVAC-Final 9/30/2024 Not Ready for Inspection DANIEL VERA
Final 10/1/2024 Corrections Issued DANIEL VERA
Footing/Foundation/Slab 10/1/2024 Approved DANIEL VERA
Green Building Final 10/1/2024 Not Ready for Inspection DANIEL VERA
MERV13>=Final 10/1/2024 Not Ready for Inspection DANIEL VERA
SGSOV-Seismic Gas S/O Valve 10/1/2024 SGSOV Approved DANIEL VERA
Smoke Detectors 10/1/2024 Approved DANIEL VERA
Gas Test 10/4/2024 Approved DANIEL VERA
HVAC-Final 10/4/2024 Corrections Issued DANIEL VERA
PLUMBING-Final 10/4/2024 Approved DANIEL VERA
Service/Power Release 10/4/2024 Approved DANIEL VERA
HVAC-Final 10/8/2024 Approved DANIEL VERA
ELECTRICAL-Final 10/29/2024 Approved DANIEL VERA
Final 10/29/2024 OK to Issue CofO DANIEL VERA
Green Building Final 10/29/2024 Approved DANIEL VERA
HVAC-Final 10/29/2024 Approved DANIEL VERA
MERV13>=Final 10/29/2024 Approved DANIEL VERA
PLUMBING-Final 10/29/2024 Approved DANIEL VERA