771 N EL MEDIO AVE 90272

Certificate Information: 771 N EL MEDIO AVE 90272

Application / Permit
23014-30000-04038
Plan Check / Job No.
B23WL02504
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition and remodel to (e) 2-story SFD w./ att. 1-car garage
Permit Issued
Issued on 3/7/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 REZA HAGHIGHAT
Corrections Issued 10/15/2023 REZA HAGHIGHAT
Quality Review Completed 10/24/2023 KAVIAN REFAHI
Building Plans Picked Up 10/31/2023 APPLICANT
Applicant returned to address corrections 1/24/2024 REZA HAGHIGHAT
Plan Check Approved 3/7/2024 REZA HAGHIGHAT
Issued 3/7/2024 APPLICANT
CofO in Progress 12/20/2024 EVAN COOPER
Permit Finaled 12/24/2024 RICHARD STEINBACH
CofO Issued 12/24/2024 RICHARD STEINBACH
Permit Finaled 12/24/2024 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 1/9/2024 SAMUEL LINN
Permit Cleared 1/16/2024 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 1/17/2024 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 1/17/2024 KIMBERLY HERNANDEZ
Sewer availability Cleared 1/17/2024 KIMBERLY HERNANDEZ
GPI Written Notices Cleared 1/24/2024 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 1/24/2024 REZA HAGHIGHAT

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

MEL KHACHATOURIAN, (213) 796-6439 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/13/2024 Partial Approval EVAN COOPER
Footing/Foundation/Slab 3/22/2024 Partial Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 3/26/2024 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Partial Approval EVAN COOPER
PLUMBING-Rough 3/29/2024 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 4/3/2024 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval EVAN COOPER
Green Building Rough 4/10/2024 Not Ready for Inspection EVAN COOPER
Deputy Wood Construction 4/18/2024 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 4/26/2024 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Partial Approval EVAN COOPER
ELECTRICAL-Rough 5/13/2024 Approved EVAN COOPER
PLUMBING-Rough 5/13/2024 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Partial Approval EVAN COOPER
Green Building Rough 6/3/2024 Not Ready for Inspection EVAN COOPER
HVAC-Rough 6/7/2024 Corrections Issued EVAN COOPER
Insulation 6/7/2024 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 6/7/2024 Partial Approval EVAN COOPER
Verify Sprinkler Sign Off 6/7/2024 Approved EVAN COOPER
Insulation 6/21/2024 Not Ready for Inspection EVAN COOPER
Insulation 6/26/2024 Approved EVAN COOPER
Drywall Nailing 7/3/2024 Approved EVAN COOPER
Green Building Rough 7/3/2024 Approved EVAN COOPER
Interior/Exterior Lathing 7/9/2024 Approved EVAN COOPER
Service/Power Release 8/15/2024 Approved EVAN COOPER
ELECTRICAL-Final 8/22/2024 Approved EVAN COOPER
Final 8/22/2024 Corrections Issued EVAN COOPER
HVAC-Final 8/22/2024 Approved EVAN COOPER
PLUMBING-Final 8/22/2024 Approved EVAN COOPER
BUILDING-Rough-Frame 12/20/2024 Approved EVAN COOPER
Final 12/20/2024 OK to Issue CofO EVAN COOPER
Footing/Foundation/Slab 12/20/2024 Approved EVAN COOPER
Green Building Final 12/20/2024 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Approved EVAN COOPER
Smoke Detectors 12/20/2024 Approved EVAN COOPER
Structural Steel Frame 12/20/2024 Approved EVAN COOPER