6945 N LINDLEY AVE 91335

Certificate Information: 6945 N LINDLEY AVE 91335

Application / Permit
23014-30000-04033
Plan Check / Job No.
B23WL02492
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2nd story addition and conversion of existing 2-car garage to ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 1/18/2024
Issuing Office
West Los Angeles
Current Status
Issued on 1/18/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/3/2023 APPLICANT
Assigned to Plan Check Engineer 10/5/2023 YASHAR EMAMI
Corrections Issued 10/16/2023 YASHAR EMAMI
Quality Review Completed 10/19/2023 REZA HAGHIGHAT
Building Plans Picked Up 10/20/2023 APPLICANT
Plan Check Approved 12/15/2023 YASHAR EMAMI
Issued 1/18/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/19/2023 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 11/22/2023 MELINEH AGHAKHABIAN
ZI Cleared 11/27/2023 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 12/1/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/1/2023 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 12/15/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/25/2024 Approved JEFFREY BULL
Deputy Drilled-In Anchors 1/31/2024 Approved JEFFREY BULL
Footing/Foundation/Slab 2/2/2024 Approved MORRIS JACKSON
Sewer 2/2/2024 Not Ready for Inspection MORRIS JACKSON
Sewer 2/6/2024 Approved JEFFREY BULL
Deputy Wood Construction 2/16/2024 Conditional Approval ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Approved GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 3/8/2024 Not Ready for Inspection JEFFREY BULL
HVAC-Rough 3/27/2024 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 3/27/2024 Not Ready for Inspection DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 4/1/2024 Approved JEFFREY BULL
Special/Order Compliance 4/1/2024 Corrections Issued JEFFREY BULL
Deputy Wood Construction 4/5/2024 Conditional Approval JEFFREY BULL
Interior/Exterior Lathing 4/11/2024 Partial Approval JEFFREY BULL
Insulation 4/22/2024 No Access for Inspection JEFFREY BULL
Drywall Nailing 5/13/2024 Approved JEFFREY BULL
Green Building Rough 5/13/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 6/6/2024 Not Ready for Inspection MORRIS JACKSON
Shower Pan 6/6/2024 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 6/10/2024 Not Ready for Inspection ALEXANDER HANDY
Shower Pan 6/10/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 12/26/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 12/26/2024 Approved ARUTYUN MADATYAN
Final 12/26/2024 Corrections Issued ARUTYUN MADATYAN
Green Building Final 12/26/2024 Approved ARUTYUN MADATYAN
Grounding or Bonding 12/26/2024 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 12/26/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 12/26/2024 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 12/26/2024 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 12/26/2024 Approved ARUTYUN MADATYAN
Service/Power Release 3/17/2025 Approved ARUTYUN MADATYAN
Final 1/21/2026 Not Ready for Inspection ARUTYUN MADATYAN