- interior remodel and addition to an existing SFD wit attached garage *** 1 of 3 ***
- Permit Issued
- Issued on 4/30/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 4/30/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2023 | KAVIAN REFAHI |
| Corrections Issued | 10/19/2023 | KAVIAN REFAHI |
| Quality Review Completed | 10/23/2023 | REZA HAGHIGHAT |
| Building Plans Picked Up | 10/24/2023 | APPLICANT |
| Applicant returned to address corrections | 11/20/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 12/4/2023 | KAVIAN REFAHI |
| Plan Check Approved | 4/29/2024 | KAVIAN REFAHI |
| Issued | 4/30/2024 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/30/2023 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 10/30/2023 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 10/30/2023 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 10/30/2023 | DARIN LAM |
| BHO/Hillside ordinance | Cleared | 10/30/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 10/31/2023 | DARIN LAM |
| Sewer availability | Cleared | 10/31/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2023 | DARIN LAM |
| GPI Written Notices | Cleared | 11/20/2023 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 11/20/2023 | KAVIAN REFAHI |
| Hydrant and Access approval | Cleared | 12/2/2023 | JOHN CONNEALLY |
Contact Information
| Contractor | Bespoke Builders; Lic. No.: 1107603-B | 269 S BEVERLY DRIVE #924 BEVERLY HILLS, CA 90212 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
| Geologist | Irvine,, Jon Alan; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2024 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/23/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/23/2024 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/27/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/27/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2024 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/6/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 11/6/2024 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/8/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 11/8/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 11/8/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 11/14/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 11/14/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/3/2024 | Corrections Issued | EVAN COOPER |
| Sewer | 12/3/2024 | Approved | EVAN COOPER |
| Underground Mechanical | 12/18/2024 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/20/2024 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/23/2024 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/26/2024 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 12/26/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/26/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/30/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 12/30/2024 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 12/30/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 1/6/2025 | Partial Approval | KEVIN SARGSYAN |
| Green Building Rough | 1/6/2025 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 1/10/2025 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 1/27/2025 | Approved | KEVIN SARGSYAN |
| Shower Pan | 1/31/2025 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 2/3/2025 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 2/10/2025 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/27/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/9/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 12/15/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 12/22/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 12/22/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 2/26/2026 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 3/2/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Final | 3/9/2026 | Approved | KEVIN SARGSYAN |