635 N BONHILL ROAD 90049

Certificate Information: 635 N BONHILL ROAD 90049

Application / Permit
23014-30000-04029
Plan Check / Job No.
B23WL02488
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
interior remodel and addition to an existing SFD wit attached garage *** 1 of 3 ***
Permit Issued
Issued on 4/30/2024
Issuing Office
West Los Angeles
Current Status
Issued on 4/30/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/9/2023 APPLICANT
Assigned to Plan Check Engineer 10/12/2023 KAVIAN REFAHI
Corrections Issued 10/19/2023 KAVIAN REFAHI
Quality Review Completed 10/23/2023 REZA HAGHIGHAT
Building Plans Picked Up 10/24/2023 APPLICANT
Applicant returned to address corrections 11/20/2023 KAVIAN REFAHI
Applicant returned to address corrections 12/4/2023 KAVIAN REFAHI
Plan Check Approved 4/29/2024 KAVIAN REFAHI
Issued 4/30/2024 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/30/2023 DARIN LAM
BHO/Hillside ordinance Cleared 10/30/2023 DARIN LAM
BHO/Hillside ordinance Cleared 10/30/2023 DARIN LAM
BHO/Hillside ordinance Cleared 10/30/2023 DARIN LAM
BHO/Hillside ordinance Cleared 10/30/2023 DARIN LAM
Roof/Waste drainage to street Cleared 10/31/2023 DARIN LAM
Sewer availability Cleared 10/31/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 11/1/2023 DARIN LAM
GPI Written Notices Cleared 11/20/2023 KAVIAN REFAHI
Grading Pre-Inspection Cleared 11/20/2023 KAVIAN REFAHI
Hydrant and Access approval Cleared 12/2/2023 JOHN CONNEALLY

Contact Information

Contractor Bespoke Builders; Lic. No.: 1107603-B 269 S BEVERLY DRIVE #924      BEVERLY HILLS, CA 90212
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Geologist Irvine,, Jon Alan; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/18/2024 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 7/23/2024 Approved KEVIN SARGSYAN
PLUMBING-Rough 8/23/2024 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 8/27/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 8/27/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/20/2024 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 11/6/2024 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 11/6/2024 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 11/8/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 11/8/2024 Corrections Issued BOBBY KEY
HVAC-Rough 11/8/2024 Approved BOBBY KEY
ELECTRICAL-Rough 11/14/2024 Approved BOBBY KEY
PLUMBING-Rough 11/14/2024 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/18/2024 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/2/2024 Approved KEVIN SARGSYAN
PLUMBING-Rough 12/3/2024 Corrections Issued EVAN COOPER
Sewer 12/3/2024 Approved EVAN COOPER
Underground Mechanical 12/18/2024 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 12/20/2024 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 12/23/2024 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 12/26/2024 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 12/26/2024 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 12/26/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 12/30/2024 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 12/30/2024 Partial Approval KEVIN SARGSYAN
HVAC-Rough 12/30/2024 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 1/6/2025 Partial Approval KEVIN SARGSYAN
Green Building Rough 1/6/2025 Partial Approval KEVIN SARGSYAN
Insulation 1/10/2025 Approved KEVIN SARGSYAN
Drywall Nailing 1/27/2025 Approved KEVIN SARGSYAN
Shower Pan 1/31/2025 Corrections Issued KEVIN SARGSYAN
Shower Pan 2/3/2025 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 2/10/2025 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 2/27/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 12/9/2025 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 12/15/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 12/22/2025 Approved KEVIN SARGSYAN
PLUMBING-Final 12/22/2025 Approved KEVIN SARGSYAN
HVAC-Final 2/26/2026 Corrections Issued KEVIN SARGSYAN
HVAC-Final 3/2/2026 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Final 3/9/2026 Approved KEVIN SARGSYAN