531 W 53RD ST 90037

Certificate Information: 531 W 53RD ST 90037

Application / Permit
23014-30000-03871
Plan Check / Job No.
B23WL02402
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and Remodel of (E) Single-Story SFD; scope of work to include: enclosing front covered porch, new front addition, and remodel of (E) SFD
Permit Issued
Issued on 10/25/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/22/2023 APPLICANT
Assigned to Plan Check Engineer 9/29/2023 RICHARD GARCIA
Corrections Issued 9/29/2023 RICHARD GARCIA
Plan Check Approved 10/20/2023 AMY GUEVARRA
Issued 10/25/2023 APPLICANT
CofO in Progress 6/25/2024 SABAS ALONSO
CofO Issued 6/27/2024 DEROLD HAUFF
Permit Finaled 6/27/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/4/2023 JUSTIN BICOL
Roof/Waste drainage to street Cleared 10/4/2023 JUSTIN BICOL
Sewer availability Cleared 10/4/2023 JUSTIN BICOL

Contact Information

Architect Park,, Sang Hun; Lic. No.: C33387 1424 4TH ST. #700B      SANTA MONICA, CA 90401
Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/15/2023 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 11/29/2023 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 12/4/2023 Approved SABAS ALONSO
Underground Mechanical 12/4/2023 Corrections Issued SABAS ALONSO
Underground Mechanical 12/12/2023 Corrections Issued SABAS ALONSO
HVAC-Rough 2/13/2024 Approved SABAS ALONSO
Sewer 2/13/2024 Approved SABAS ALONSO
Deputy Wood Construction 2/14/2024 Conditional Approval SABAS ALONSO
ELECTRICAL-Rough 2/20/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/20/2024 Approved SABAS ALONSO
PLUMBING-Rough 2/20/2024 Approved SABAS ALONSO
Underground Mechanical 2/20/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 2/28/2024 Approved SABAS ALONSO
Green Building Rough 2/28/2024 Approved SABAS ALONSO
MERV13>=Rough 2/28/2024 Approved SABAS ALONSO
Shower Pan 2/28/2024 Corrections Issued SABAS ALONSO
Insulation 3/6/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 3/6/2024 Partial Approval JOSH MEISTER
Shower Pan 3/6/2024 Approved JOSH MEISTER
Drywall Nailing 3/13/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 3/13/2024 Approved JOSH MEISTER
ELECTRICAL-Final 5/29/2024 Corrections Issued SABAS ALONSO
Gas Test 5/29/2024 Approved SABAS ALONSO
PLUMBING-Final 5/29/2024 Approved SABAS ALONSO
ELECTRICAL-Final 6/6/2024 Not Ready for Inspection SABAS ALONSO
Final 6/6/2024 Corrections Issued SABAS ALONSO
Green Building Final 6/6/2024 Corrections Issued SABAS ALONSO
HVAC-Final 6/6/2024 Corrections Issued SABAS ALONSO
MERV13>=Final 6/6/2024 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/6/2024 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 6/6/2024 Approved SABAS ALONSO
ELECTRICAL-Final 6/14/2024 Not Ready for Inspection SABAS ALONSO
Final 6/14/2024 Corrections Issued SABAS ALONSO
Green Building Final 6/14/2024 Approved SABAS ALONSO
HVAC-Final 6/14/2024 Approved SABAS ALONSO
MERV13>=Final 6/14/2024 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/14/2024 SGSOV Approved SABAS ALONSO
Final 6/24/2024 OK to Issue CofO SABAS ALONSO
MERV13>=Final 6/24/2024 Approved SABAS ALONSO