6030 1/2-3/4 N COLFAX AVE 91606

Certificate Information: 6030 1/2-3/4 N COLFAX AVE 91606

Application / Permit
23014-30000-03865
Plan Check / Job No.
B23VN11194
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** 2- story Detached (2) ADU PER CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 2/1/2024
Issuing Office
Current Status
CofO Issued on 8/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2023 APPLICANT
Assigned to Plan Check Engineer 8/31/2023 YASHAR EMAMI
Corrections Issued 9/4/2023 YASHAR EMAMI
Quality Review Completed 9/11/2023 CHIHARU SUZUKI
Applicant returned to address corrections 9/22/2023 YASHAR EMAMI
Applicant returned to address corrections 9/28/2023 YASHAR EMAMI
Applicant returned to address corrections 10/11/2023 YASHAR EMAMI
Applicant returned to address corrections 11/30/2023 YASHAR EMAMI
Applicant returned to address corrections 12/7/2023 YASHAR EMAMI
Applicant returned to address corrections 1/9/2024 YASHAR EMAMI
Plan Check Approved 1/17/2024 YASHAR EMAMI
Plan Check Approved 1/24/2024 YASHAR EMAMI
Issued 2/1/2024 APPLICANT
CofO in Progress 7/14/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 8/27/2025 RUBEN SALAS
CofO Issued 8/27/2025 RUBEN SALAS
Permit Finaled 8/27/2025 RUBEN SALAS

Permit Application Clearance Information

Tenant Habitability Plan Cleared 9/26/2023 RICARDO BOHORQUEZ
Address approval Cleared 9/28/2023 COLIN LOREDO
"Q" conditions Cleared 11/1/2023 ALEX VELA
Frnt yard landscape/Water mgmt Cleared 11/1/2023 ALEX VELA
Eng Process Fee Ord 176,300 Cleared 11/16/2023 COLIN LOREDO
Sewer availability Cleared 11/16/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 1/2/2024 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/4/2024 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: C87661 22430 CRISWELL ST      WEST HILLS, CA 91307

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/6/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 6/13/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 6/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 6/24/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 6/27/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 7/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 8/5/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/8/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Wood Frame 8/8/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 9/19/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/27/2024 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 9/27/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 9/27/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 10/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 10/9/2024 Conditional Approval JUAN VALENZUELA
Rough-Elec/Plmb/HVAC 10/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Wood Frame 10/18/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 11/8/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 11/13/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 11/13/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 11/13/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 11/13/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 11/21/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Wood Frame 11/21/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Shower Pan 11/22/2024 No Access for Inspection JOSE AVILA
BUILDING-Rough-Frame 12/6/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 12/6/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 12/6/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 12/11/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 12/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Sewer 1/16/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 1/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/2/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 4/2/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 4/2/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/2/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/2/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/2/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Deputy Steel/Welding 4/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 4/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 4/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 4/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/15/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 6/6/2025 No Access for Inspection MISAEL ESPARZA
Green Building Final 6/6/2025 No Access for Inspection MISAEL ESPARZA
Service/Power Release 6/6/2025 No Access for Inspection MISAEL ESPARZA
Final 6/11/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 6/11/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Service/Power Release 6/11/2025 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Final 6/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 6/20/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 6/20/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 7/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 7/14/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/14/2025 Approved ROBERTO PALACIOS-LOPEZ