6030 1/2-3/4 N COLFAX AVE 91606
Certificate Information: 6030 1/2-3/4 N COLFAX AVE 91606
- Application / Permit
- 23014-30000-03865
- Plan Check / Job No.
- B23VN11194
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** 2- story Detached (2) ADU PER CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 2/1/2024
- Issuing Office
- Current Status
- CofO Issued on 8/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | YASHAR EMAMI |
| Corrections Issued | 9/4/2023 | YASHAR EMAMI |
| Quality Review Completed | 9/11/2023 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 9/22/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 9/28/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 10/11/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 11/30/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 12/7/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 1/9/2024 | YASHAR EMAMI |
| Plan Check Approved | 1/17/2024 | YASHAR EMAMI |
| Plan Check Approved | 1/24/2024 | YASHAR EMAMI |
| Issued | 2/1/2024 | APPLICANT |
| CofO in Progress | 7/14/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 8/27/2025 | RUBEN SALAS |
| CofO Issued | 8/27/2025 | RUBEN SALAS |
| Permit Finaled | 8/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/26/2023 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 9/28/2023 | COLIN LOREDO |
| "Q" conditions | Cleared | 11/1/2023 | ALEX VELA |
| Frnt yard landscape/Water mgmt | Cleared | 11/1/2023 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 11/16/2023 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 1/2/2024 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/4/2024 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/6/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/13/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/24/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/27/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 7/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 8/5/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/8/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 8/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 9/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 9/27/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 9/27/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 10/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 10/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 10/9/2024 | Conditional Approval | JUAN VALENZUELA |
| Rough-Elec/Plmb/HVAC | 10/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 10/18/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 11/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/13/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 11/13/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/13/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 11/13/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 11/21/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 11/21/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 11/22/2024 | No Access for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 12/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 12/6/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 12/6/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 12/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 12/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Sewer | 1/16/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 1/16/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/2/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 4/2/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 4/2/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Not Required | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 4/2/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 4/2/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 4/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Deputy Steel/Welding | 4/10/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 4/10/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 4/10/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 4/10/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 4/10/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 4/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 4/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 4/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 4/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 4/24/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 6/6/2025 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Final | 6/6/2025 | No Access for Inspection | MISAEL ESPARZA |
| Service/Power Release | 6/6/2025 | No Access for Inspection | MISAEL ESPARZA |
| Final | 6/11/2025 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 6/11/2025 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 6/11/2025 | No Access for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 6/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 6/20/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 6/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 7/8/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/8/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 7/14/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |