4224 N BAKMAN AVE 91602

Certificate Information: 4224 N BAKMAN AVE 91602

Application / Permit
23014-30000-03844
Plan Check / Job No.
B23WL02385
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and 2-story addition to (e) 1-story SFD, add an attached 2-car garage
Permit Issued
Issued on 12/13/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 YASHAR EMAMI
Corrections Issued 10/5/2023 YASHAR EMAMI
Quality Review Completed 10/5/2023 REZA HAGHIGHAT
Building Plans Picked Up 10/6/2023 APPLICANT
Plan Check Approved 11/16/2023 YASHAR EMAMI
Issued 12/13/2023 APPLICANT
CofO in Progress 11/20/2024 JUAN VALENZUELA
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 10/6/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 10/10/2023 NIKKI ZULUETA
ZI Cleared 10/17/2023 NATHAN ROMINE
Low Impact Development (LID) Cleared 10/24/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 10/30/2023 NIKKI ZULUETA
Sewer availability Cleared 11/1/2023 NIKKI ZULUETA
Trees in Parkway Cleared 11/13/2023 ADALBERTO VERA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Bems Construction; Lic. No.: 1014009-B 3121 E CORTO PL APT #1      LONG BEACH, CA 90803
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/15/2023 Corrections Issued KIRK SANDERS
Sewer 1/19/2024 Partial Approval KIRK SANDERS
Underground Mechanical 1/19/2024 Partial Approval KIRK SANDERS
Excavation/Setback/Form/Re-Bar 1/31/2024 Approved KIRK SANDERS
Footing/Foundation/Slab 1/31/2024 Approved KIRK SANDERS
Deputy Drilled-In Anchors 2/1/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/13/2024 Partial Approval DAVID ANDERSON
Deputy Wood Construction 4/23/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Approved JACK KARGODORIAN
ELECTRICAL-Rough 5/29/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 5/29/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 5/29/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/3/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 6/3/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/6/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 6/6/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 6/6/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 6/13/2024 Approved CHRISTOPHER ROJAS
Insulation 6/13/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/13/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 6/20/2024 Approved CHRISTOPHER ROJAS
Sewer 8/7/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 10/21/2024 Corrections Issued CHRISTOPHER ROJAS
Gas Test 10/21/2024 Corrections Issued CHRISTOPHER ROJAS
Gas Test 10/25/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Final 10/25/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 10/30/2024 Approved CHRISTOPHER ROJAS
Service/Power Release 10/30/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/18/2024 Approved JUAN VALENZUELA
Final 11/18/2024 OK to Issue CofO JUAN VALENZUELA
Green Building Final 11/18/2024 Approved JUAN VALENZUELA
HVAC-Final 11/18/2024 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 11/18/2024 Approved JUAN VALENZUELA