526 N SWARTHMORE AVE 90272

Certificate Information: 526 N SWARTHMORE AVE 90272

Application / Permit
23014-30000-03816
Plan Check / Job No.
B23WL02360
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition w/ new basement to a S.F.D.
Permit Issued
Issued on 11/30/2023
Issuing Office
West Los Angeles
Current Status
Issued on 11/30/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/20/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 HOOMAN HAJIZADEH
Corrections Issued 9/29/2023 HOOMAN HAJIZADEH
Quality Review Completed 10/3/2023 KAVIAN REFAHI
Building Plans Picked Up 10/6/2023 APPLICANT
Plan Check Approved 11/29/2023 HOOMAN HAJIZADEH
Issued 11/30/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/24/2023 DINAH GARIN
Sewer availability Cleared 10/24/2023 DINAH GARIN
Low Impact Development (LID) Cleared 11/3/2023 SAMUEL LINN
Hydrant and Access approval Cleared 11/7/2023 KURT CORRAL
Roof/Waste drainage to street Cleared 11/8/2023 DINAH GARIN
Coastal Zone Cleared 11/9/2023 MAXFIELD VERMY
Miscellaneous Cleared 11/9/2023 MAXFIELD VERMY
GPI Written Notices Cleared 11/29/2023 HOOMAN HAJIZADEH
Grading Pre-Inspection Cleared 11/29/2023 HOOMAN HAJIZADEH

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Town & Country Construction; Lic. No.: 924332-B 2780 SANTA MARIA RD      TOPANGA, CA 90290
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Le,, Thang Huu; Lic. No.: C63174 507 MAGELLAN RD      ARCADIA, CA 91007
Geologist Feffer,, Joshua R; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/24/2024 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 7/5/2024 Partial Approval EVAN COOPER
Deputy Shotcrete 7/25/2024 Conditional Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 7/26/2024 Partial Approval EVAN COOPER
Deputy Shotcrete 7/29/2024 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 10/8/2024 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 10/18/2024 Partial Approval EVAN COOPER
Deputy Wood Construction 11/5/2024 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Partial Approval EVAN COOPER
Deputy Drilled-In Anchors 11/8/2024 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 11/14/2024 Approved EVAN COOPER
Deputy Wood Construction 11/25/2024 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Partial Approval EVAN COOPER
Deputy Wood Construction 12/18/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/18/2024 Partial Approval ARAM AVEDISIAN
Deputy Wood Construction 12/20/2024 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Partial Approval EVAN COOPER