617 1/2 N MCCADDEN PL 90004

Certificate Information: 617 1/2 N MCCADDEN PL 90004

Application / Permit
23014-30000-03811
Plan Check / Job No.
B23WL02357
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition of 4'x5' (20sf) to (E) dettached garage and conversion into an Accessory Dwelling Unit per LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 4/10/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2023 APPLICANT
Assigned to Plan Check Engineer 9/27/2023 RICHARD GARCIA
Corrections Issued 9/27/2023 RICHARD GARCIA
Building Plans Picked Up 10/3/2023 APPLICANT
Applicant returned to address corrections 7/29/2024 EDWIN ESPIN
Plan Check Approved 12/12/2024 JAHANSHAH POURHASSAN
Issued 4/10/2025 APPLICANT
CofO in Progress 4/1/2026 CRAIG VAUGHAN
Permit Finaled 4/2/2026 DEROLD HAUFF
CofO Issued 4/2/2026 DEROLD HAUFF
Permit Finaled 4/2/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/26/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 2/26/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 3/22/2024 DAVID LOPEZ
Sewer availability Cleared 3/22/2024 DAVID LOPEZ
Construction near power lines Cleared 4/26/2024 RIDWAN HARDY
Construction within easement Cleared 4/26/2024 RIDWAN HARDY
HPOZ Cleared 12/11/2024 SUKI GERSHENHORN

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/14/2025 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 4/14/2025 Not Ready for Inspection CRAIG VAUGHAN
METHANE-Barrier 4/14/2025 Not Ready for Inspection CRAIG VAUGHAN
METHANE-Subgrade 4/14/2025 Not Ready for Inspection CRAIG VAUGHAN
Sewer 4/14/2025 Approved CRAIG VAUGHAN
Underground Mechanical 4/14/2025 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/18/2025 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 4/18/2025 Corrections Issued CRAIG VAUGHAN
METHANE-Barrier 4/18/2025 Approved CRAIG VAUGHAN
METHANE-Subgrade 4/18/2025 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/22/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 6/16/2025 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 6/16/2025 Not Ready for Inspection CRAIG VAUGHAN
METHANE-Rough 6/16/2025 Approved CRAIG VAUGHAN
Wood Frame 6/16/2025 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 7/2/2025 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 7/2/2025 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 7/22/2025 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 7/22/2025 Corrections Issued CRAIG VAUGHAN
Green Building Rough 7/22/2025 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/22/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 7/29/2025 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 7/29/2025 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 7/29/2025 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 7/29/2025 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 7/31/2025 Partial Approval CRAIG VAUGHAN
HVAC-Rough 7/31/2025 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 7/31/2025 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 8/8/2025 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 8/8/2025 Partial Approval CRAIG VAUGHAN
Green Building Rough 8/8/2025 Partial Approval CRAIG VAUGHAN
HVAC-Rough 8/8/2025 Partial Approval CRAIG VAUGHAN
Insulation 8/14/2025 Approved ROY SPAULDING
Drywall Nailing 8/19/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 8/19/2025 Approved REGINA MENDEZ
Shower Pan 8/19/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 10/3/2025 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 12/17/2025 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 12/17/2025 Not Ready for Inspection CRAIG VAUGHAN
Final 12/17/2025 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 12/17/2025 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 12/17/2025 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 12/17/2025 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 12/17/2025 Not Ready for Inspection CRAIG VAUGHAN
METHANE-Subgrade 12/17/2025 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 12/17/2025 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 12/17/2025 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 1/28/2026 Approved CRAIG VAUGHAN
ELECTRICAL-Final 1/28/2026 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 1/28/2026 Approved CRAIG VAUGHAN
Green Building Final 1/28/2026 Approved CRAIG VAUGHAN
Green Building Rough 1/28/2026 Approved CRAIG VAUGHAN
HVAC-Final 1/28/2026 Corrections Issued CRAIG VAUGHAN
METHANE-Subgrade 1/28/2026 Approved CRAIG VAUGHAN
PLUMBING-Final 1/28/2026 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/28/2026 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 1/28/2026 Approved CRAIG VAUGHAN
ELECTRICAL-Final 2/6/2026 Approved CRAIG VAUGHAN
Final 2/6/2026 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Final 2/6/2026 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 2/6/2026 Approved CRAIG VAUGHAN
Final 3/12/2026 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 3/12/2026 Approved CRAIG VAUGHAN