3582 S VETERAN AVE 90034

Certificate Information: 3582 S VETERAN AVE 90034

Application / Permit
23014-30000-03711
Plan Check / Job No.
B23WL02312
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and remodel of (E) SFD
Permit Issued
Issued on 7/25/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2023 APPLICANT
Assigned to Plan Check Engineer 9/19/2023 RICHARD GARCIA
Corrections Issued 9/19/2023 RICHARD GARCIA
Building Plans Picked Up 9/26/2023 APPLICANT
Applicant returned to address corrections 12/15/2023 CAROLEAN BASMA
Plan Check Approved 2/20/2024 CAROLEAN BASMA
Issued 7/25/2024 APPLICANT
CofO in Progress 4/24/2025 WILBER ROSALES
Permit Finaled 4/28/2025 RICHARD STEINBACH
CofO Issued 4/28/2025 RICHARD STEINBACH
Permit Finaled 4/28/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/27/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/29/2023 DINAH GARIN
Specific Plan Cleared 1/10/2024 EDUARDO HERMOSO
Grading Pre-Inspection Cleared 2/20/2024 RICHARD GARCIA

Contact Information

Contractor Santiago Edgar; Lic. No.: 1094276-B 38719 27TH STREET E      PALMDALE, CA 93550
Engineer Labrada,, Luis Alfonso; Lic. No.: C65416 217 LANDIS AVE      CHULA VISTA, CA 91910

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/12/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 8/21/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/22/2024 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Approved DANIEL VERA
HVAC-Rough 9/23/2024 Approved DANIEL VERA
Wood Frame 9/23/2024 Approved DANIEL VERA
BUILDING-Rough-Frame 9/24/2024 Corrections Issued DANIEL VERA
Deputy Wood Construction 9/24/2024 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Approved DANIEL VERA
Green Building Rough 9/24/2024 Not Ready for Inspection DANIEL VERA
Wood Frame 9/24/2024 Approved DANIEL VERA
BUILDING-Rough-Frame 9/27/2024 Not Ready for Inspection DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 9/27/2024 Approved DANIEL VERA
Green Building Rough 9/27/2024 Not Ready for Inspection DANIEL VERA
Insulation 10/16/2024 Approved REGINA MENDEZ
Interior/Exterior Lathing 10/16/2024 Approved REGINA MENDEZ
BUILDING-Rough-Frame 10/18/2024 Approved DANIEL VERA
Drywall Nailing 10/18/2024 Approved DANIEL VERA
Green Building Rough 10/18/2024 Approved DANIEL VERA
Final 2/25/2025 Not Ready for Inspection JESUS RODRIGUEZ
Green Building Final 2/25/2025 Not Ready for Inspection JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/25/2025 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 2/25/2025 Not Ready for Inspection JESUS RODRIGUEZ
Final 4/18/2025 Corrections Issued ARAM AVEDISIAN
Green Building Final 4/18/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 4/18/2025 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 4/24/2025 Approved WILBER ROSALES
Final 4/24/2025 OK to Issue CofO WILBER ROSALES
HVAC-Final 4/24/2025 Approved WILBER ROSALES
PLUMBING-Final 4/24/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 4/24/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 4/24/2025 Approved WILBER ROSALES