19237-19239 W LINNET ST 91356

Certificate Information: 19237-19239 W LINNET ST 91356

Application / Permit
23014-30000-03666
Plan Check / Job No.
B23WL02284
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story SB-9 unit with attached ADU below per ordinance
Permit Issued
Issued on 9/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 HOOMAN HAJIZADEH
Corrections Issued 9/28/2023 HOOMAN HAJIZADEH
Quality Review Completed 10/3/2023 KAVIAN REFAHI
Building Plans Picked Up 10/10/2023 APPLICANT
Applicant returned to address corrections 1/24/2024 HOOMAN HAJIZADEH
Plan Check Approved 3/27/2024 HOOMAN HAJIZADEH
Issued 9/23/2024 APPLICANT
CofO in Progress 1/6/2026 JOHN KIDWELL
Permit Finaled 1/30/2026 JOHN JANSON
CofO Issued 1/30/2026 JOHN JANSON
Permit Finaled 1/30/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/20/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 10/31/2023 EDGAR ALCARAZ
Senate Bill 9 Cleared 10/31/2023 DAVID URITA
Sewer availability Cleared 10/31/2023 EDGAR ALCARAZ
Grading Pre-Inspection Cleared 11/1/2023 ALEXANDER HELFER
Construction within easement Cleared 12/15/2023 RIDWAN HARDY
Hydrant and Access approval Cleared 2/13/2024 RUEL COLE
Low Impact Development (LID) Cleared 3/12/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 3/15/2024 CARLOS AGUILERA
GPI Written Notices Cleared 3/27/2024 HOOMAN HAJIZADEH

Contact Information

Contractor Jkc Construction & Design; Lic. No.: 1007078-B 18880 WELLS DRIVE      TARZANA, CA 91356
Engineer Desai,, Anil T; Lic. No.: C24653 1530 VIA LOS COYOTES      LA HABRA, CA 90631
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/23/2024 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 10/23/2024 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 10/25/2024 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Partial Approval JOHN KIDWELL
Deputy Wood Construction 11/19/2024 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/20/2024 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 12/3/2024 Approved TROY SANDERS
Green Building Rough 12/9/2024 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 12/9/2024 Partial Approval JOHN KIDWELL
Rough-Elec/Plmb/HVAC 12/9/2024 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 12/9/2024 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 12/12/2024 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 12/17/2024 Partial Approval SCOTT SOBEL
BUILDING-Rough-Frame 12/31/2024 Approved JOHN KIDWELL
Green Building Rough 12/31/2024 Approved JOHN KIDWELL
Insulation 12/31/2024 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 12/31/2024 Approved JOHN KIDWELL
Insulation 1/3/2025 Approved JOHN KIDWELL
Drywall Nailing 1/8/2025 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/8/2025 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 3/5/2025 Not Ready for Inspection JOHN KIDWELL
Sewer 3/5/2025 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 3/5/2025 Partial Approval JOHN KIDWELL
Service/Power Release 3/12/2025 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Final 3/21/2025 Conditional Approval JOHN KIDWELL
Service/Power Release 3/21/2025 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 4/24/2025 Approved JOHN KIDWELL
PLUMBING-Final 4/24/2025 Approved JOHN KIDWELL
Sewer 4/25/2025 Conditional Approval JOHN KIDWELL
Sewer 5/2/2025 Approved JOHN KIDWELL
Final 11/24/2025 Not Ready for Inspection GEVORK IPCHYAN
Footing/Foundation/Slab 11/24/2025 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 11/24/2025 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 11/24/2025 SGSOV Not Ready GEVORK IPCHYAN
Service/Power Release 11/24/2025 Not Ready for Inspection GEVORK IPCHYAN
Smoke Detectors 11/24/2025 Not Ready for Inspection GEVORK IPCHYAN
Final 12/1/2025 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 12/1/2025 Approved JOHN KIDWELL
Green Building Final 12/1/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 12/1/2025 SGSOV Approved JOHN KIDWELL
Service/Power Release 12/1/2025 Not Ready for Inspection JOHN KIDWELL
Smoke Detectors 12/1/2025 Approved JOHN KIDWELL
Final 12/29/2025 OK to Issue CofO JOHN KIDWELL
Green Building Final 12/29/2025 Approved JOHN KIDWELL
Service/Power Release 12/29/2025 Approved JOHN KIDWELL