452-452 1/2 S BUNDY DR 90049

Certificate Information: 452-452 1/2 S BUNDY DR 90049

Application / Permit
23014-30000-03554
Plan Check / Job No.
B23WL02227
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO AND CONVERSION OF EXISTING GARAGE INTO AN ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 1/9/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2023 APPLICANT
Assigned to Plan Check Engineer 9/9/2023 RICHARD GARCIA
Corrections Issued 9/9/2023 RICHARD GARCIA
Applicant returned to address corrections 11/22/2023 EDWIN ESPIN
Plan Check Approved 1/8/2024 KAVIAN REFAHI
Issued 1/9/2024 APPLICANT
CofO in Progress 3/27/2026 HERBERT GIRON
Permit Finaled 4/3/2026 RICHARD STEINBACH
CofO Issued 4/3/2026 RICHARD STEINBACH
Permit Finaled 4/3/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/19/2023 DARIN LAM
Roof/Waste drainage to street Cleared 10/19/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 10/23/2023 DARIN LAM
Sewer availability Cleared 10/23/2023 DARIN LAM
Specific Plan Cleared 10/25/2023 MOHAMMAD HASAN
Grading Pre-Inspection Cleared 11/6/2023 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Khanlou,, Amir; Lic. No.: C87550 2603 BASIL LN      LOS ANGELES, CA 90077

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/25/2024 Partial Approval STEPHANIE SWANSON
Deputy Drilled-In Anchors 1/30/2024 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 1/30/2024 Approved ARAM AVEDISIAN
Underground Mechanical 1/30/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 5/13/2024 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Wood Construction 6/3/2024 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 6/11/2024 Not Ready for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 6/18/2024 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 8/28/2024 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 8/28/2024 Approved JESUS RODRIGUEZ
Green Building Rough 8/28/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 8/28/2024 Approved JESUS RODRIGUEZ
Wood Frame 8/28/2024 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/13/2024 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 9/13/2024 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/20/2024 Approved JESUS RODRIGUEZ
Gas Test 9/20/2024 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 9/20/2024 Approved JESUS RODRIGUEZ
Insulation 10/4/2024 Approved REGINA MENDEZ
Drywall Nailing 10/21/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 10/31/2024 Not Ready for Inspection JESUS RODRIGUEZ
Shower Pan 10/31/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/4/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/5/2025 SGSOV Not Ready HERBERT GIRON
ELECTRICAL-Final 8/22/2025 Corrections Issued HERBERT GIRON
Final 8/22/2025 Corrections Issued HERBERT GIRON
Green Building Final 8/22/2025 Corrections Issued HERBERT GIRON
HVAC-Final 8/22/2025 Corrections Issued HERBERT GIRON
PLUMBING-Final 8/22/2025 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Approved HERBERT GIRON
Smoke Detectors 8/22/2025 Approved HERBERT GIRON
Final 9/19/2025 No Access for Inspection HERBERT GIRON
Green Building Final 9/19/2025 No Access for Inspection HERBERT GIRON
Final 9/23/2025 Not Ready for Inspection HERBERT GIRON
Green Building Final 9/23/2025 Approved HERBERT GIRON
HVAC-Final 9/23/2025 Approved HERBERT GIRON
Final 12/12/2025 Corrections Issued HERBERT GIRON
Final 12/17/2025 Not Ready for Inspection HERBERT GIRON
Final 2/20/2026 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 3/24/2026 Approved HERBERT GIRON
Final 3/24/2026 OK to Issue CofO HERBERT GIRON
PLUMBING-Final 3/24/2026 Approved HERBERT GIRON
Service/Power Release 3/24/2026 Approved HERBERT GIRON