149 E 69TH ST 90003

Certificate Information: 149 E 69TH ST 90003

Application / Permit
23014-30000-03500
Plan Check / Job No.
B23WL02197
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
major remodel and 2nd story addition to existing 1-story SFD by keeping portion of wall.
Permit Issued
Issued on 12/8/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2023 APPLICANT
Assigned to Plan Check Engineer 9/6/2023 HOOMAN HAJIZADEH
Corrections Issued 9/12/2023 HOOMAN HAJIZADEH
Quality Review Completed 9/19/2023 KAVIAN REFAHI
Building Plans Picked Up 9/22/2023 APPLICANT
Applicant returned to address corrections 11/15/2023 HOOMAN HAJIZADEH
Applicant returned to address corrections 12/1/2023 HOOMAN HAJIZADEH
Plan Check Approved 12/8/2023 HOOMAN HAJIZADEH
Issued 12/8/2023 APPLICANT
CofO in Progress 4/30/2024 ALEJANDRO DE ARTOLA
Permit Finaled 5/1/2024 DEROLD HAUFF
CofO Issued 5/1/2024 DEROLD HAUFF
Permit Finaled 5/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/28/2023 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 9/28/2023 AMBER CAMPBELL
Sewer availability Cleared 9/28/2023 AMBER CAMPBELL
Low Impact Development (LID) Cleared 11/2/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/3/2023 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Montemayor,, G F; Lic. No.: C25258 1617 S WAVERLY GLEN WAY      HACIENDA HEIGHTS, CA 91745

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/15/2023 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 12/19/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 12/19/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 12/28/2023 Partial Approval MICHAEL LEWIS
Deputy Wood Construction 1/4/2024 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Approved SABAS ALONSO
HVAC-Rough 1/11/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 1/11/2024 Approved MICHAEL LEWIS
Sewer 1/11/2024 Approved MICHAEL LEWIS
Shower Pan 1/11/2024 Approved MICHAEL LEWIS
Underground Mechanical 1/11/2024 Corrections Issued MICHAEL LEWIS
BUILDING-Rough-Frame 1/24/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 1/24/2024 Corrections Issued MICHAEL LEWIS
Green Building Rough 1/24/2024 Approved MICHAEL LEWIS
Insulation 1/30/2024 Approved MICHAEL LEWIS
Drywall Nailing 2/7/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 2/7/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 2/13/2024 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 3/22/2024 Partial Approval STUART CHAPMAN
ELECTRICAL-Final 4/24/2024 Approved MICHAEL LEWIS
Final 4/24/2024 Corrections Issued MICHAEL LEWIS
Gas Test 4/24/2024 Approved MICHAEL LEWIS
Green Building Final 4/24/2024 Approved MICHAEL LEWIS
HVAC-Final 4/24/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Final 4/24/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 4/24/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 4/24/2024 Approved MICHAEL LEWIS
Smoke Detectors 4/24/2024 Approved MICHAEL LEWIS
Final 4/29/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
HVAC-Final 4/29/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 4/29/2024 Approved ALEJANDRO DE ARTOLA