4122 S EAST BLVD 90066
Certificate Information: 4122 S EAST BLVD 90066
- Application / Permit
- 23014-30000-03378
- Plan Check / Job No.
- B23WL02110
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert garage portion of garage and storage room to ADU with irregular shape ground floor addition for ADU pe LAMC 12.22A.33(c) & (d). ***See Comments***
- Permit Issued
- Issued on 2/7/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2023 | JAHANSHAH POURHASSAN |
| Corrections Issued | 8/29/2023 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 8/30/2023 | APPLICANT |
| Applicant returned to address corrections | 10/25/2023 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 11/3/2023 | RICHARD GARCIA |
| Issued | 2/7/2024 | APPLICANT |
| CofO in Progress | 12/5/2024 | JESUS PINEDA |
| CofO Issued | 12/9/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/9/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/19/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2023 | DARIN LAM |
| Sewer availability | Cleared | 9/20/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 9/26/2023 | DARIN LAM |
| Hydrant and Access approval | Cleared | 10/22/2023 | JOHN CONNEALLY |
Contact Information
| Architect | Memarzadeh-Esfahani,, Mojdeh; Lic. No.: C39020 | 206 PACIFIC AVE VENICE, CA 90291 |
| Contractor | Montanari Construction; Lic. No.: 231180-B | 2402 31ST STREET SANTA MONICA, CA 90405 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/8/2024 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/13/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Special/Order Compliance | 3/14/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/26/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/17/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/17/2024 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 6/4/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 6/4/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 6/4/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/13/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 6/13/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 6/13/2024 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 6/13/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 6/25/2024 | Approved | HERBERT GIRON |
| Drywall Nailing | 7/2/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/22/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 7/22/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 8/19/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Underground Mechanical | 8/19/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/3/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 9/24/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 10/28/2024 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 10/28/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 10/28/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 11/6/2024 | Approved | JESUS PINEDA |
| Final | 11/6/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 11/6/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 11/6/2024 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 11/6/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 12/4/2024 | Approved | JESUS PINEDA |
| Final | 12/4/2024 | OK to Issue CofO | JESUS PINEDA |
| Service/Power Release | 12/4/2024 | Approved | JESUS PINEDA |