2611 S GRAND CL 90291

Certificate Information: 2611 S GRAND CL 90291

Application / Permit
23014-30000-03353
Plan Check / Job No.
B23WL02104
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST AND SECOND FLOOR REMODEL OF (E) 2-STORY SINGLE FAMILY RESIDENCE.
Permit Issued
Issued on 5/7/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2023 APPLICANT
Assigned to Plan Check Engineer 8/31/2023 KAVIAN REFAHI
Corrections Issued 9/2/2023 KAVIAN REFAHI
Quality Review Completed 9/7/2023 CHIHARU SUZUKI
Building Plans Picked Up 3/1/2024 APPLICANT
Applicant returned to address corrections 4/19/2024 KAVIAN REFAHI
Plan Check Approved 5/6/2024 KAVIAN REFAHI
Issued 5/7/2024 APPLICANT
CofO in Progress 3/26/2025 JESUS RODRIGUEZ
CofO Issued 3/26/2025 RICHARD STEINBACH
Permit Finaled 3/26/2025 RICHARD STEINBACH

Permit Application Clearance Information

Coastal Zone Cleared 1/18/2024 JAZMIN ROQUE
Coastal Zone Cleared 1/18/2024 JAZMIN ROQUE
ZA Case Cleared 1/18/2024 JAZMIN ROQUE
ZA Case Cleared 1/18/2024 JAZMIN ROQUE
ZA Case Cleared 1/18/2024 JAZMIN ROQUE
City Hist. Cultural Monument Cleared 3/21/2024 MELISSA JONES
HPOZ Cleared 3/21/2024 MELISSA JONES
Historic monument Cleared 3/21/2024 MELISSA JONES
Roof/Waste drainage to street Cleared 3/22/2024 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 3/26/2024 HISASHI KOBAYAKAWA
Sewer availability Cleared 3/26/2024 HISASHI KOBAYAKAWA
Specific Plan Cleared 4/2/2024 SIENNA KUO
Specific Plan Cleared 4/11/2024 PEDRO AYALA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Kook & Associates Construction Inc; Lic. No.: 820560-B 2100 SAWTELLE BLVD #306      LOS ANGELES, CA 90025
Engineer Namdar,, Mansour; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/13/2024 Approved HERBERT GIRON
Deputy Steel/Welding 6/21/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Corrections Issued HERBERT GIRON
Structural Steel Frame 7/1/2024 Corrections Issued HERBERT GIRON
Deputy Wood Construction 7/2/2024 Conditional Approval HERBERT GIRON
BUILDING-Rough-Frame 7/11/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 7/11/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Partial Approval HERBERT GIRON
HVAC-Rough 9/5/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Approved HERBERT GIRON
PLUMBING-Rough 9/10/2024 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 9/11/2024 Corrections Issued HERBERT GIRON
Shower Pan 9/11/2024 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 9/12/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 9/16/2024 Approved HERBERT GIRON
Shower Pan 9/16/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 9/25/2024 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 9/25/2024 Partial Approval HERBERT GIRON
Insulation 10/7/2024 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 10/9/2024 Not Ready for Inspection DAVID FEILER
Green Building Rough 10/9/2024 Not Ready for Inspection DAVID FEILER
Insulation 10/9/2024 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 10/10/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 10/15/2024 Approved HERBERT GIRON
Green Building Rough 10/15/2024 Approved HERBERT GIRON
HVAC-Rough 10/15/2024 Approved HERBERT GIRON
Insulation 10/15/2024 Approved HERBERT GIRON
PLUMBING-Rough 10/15/2024 Approved HERBERT GIRON
Drywall Nailing 10/22/2024 Approved HERBERT GIRON
Smoke Detectors 10/22/2024 Corrections Issued HERBERT GIRON
Gas Test 2/20/2025 Approved HERBERT GIRON
PLUMBING-Final 3/4/2025 Corrections Issued HERBERT GIRON
HVAC-Final 3/5/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 3/6/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 3/12/2025 Approved JESUS RODRIGUEZ
HVAC-Final 3/12/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 3/12/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Approved JESUS RODRIGUEZ
Final 3/17/2025 Corrections Issued JESUS RODRIGUEZ
Green Building Final 3/17/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/17/2025 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 3/17/2025 Approved JESUS RODRIGUEZ
Final 3/25/2025 OK to Issue CofO JESUS RODRIGUEZ
Special/Order Compliance 3/25/2025 Partial Inspection JAYLIN GRAVITTE