829 1/2 E 111TH PL 90059
Certificate Information: 829 1/2 E 111TH PL 90059
- Application / Permit
- 23014-30000-03137
- Plan Check / Job No.
- B23WL01998
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT AND ADD TO (E) DETACHED GARAGE TO CREATE 3-BR/ 3-BATH, TWO STORY ADU AT REAR YARD per LAMC 12.22 A.33 (c) and (d)
- Permit Issued
- Issued on 9/11/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/10/2023 | RICHARD GARCIA |
| Corrections Issued | 8/10/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 8/18/2023 | APPLICANT |
| Plan Check Approved | 8/30/2023 | DAVID CASTILLO |
| Issued | 9/11/2023 | APPLICANT |
| CofO in Progress | 7/12/2024 | ANSON MAGLASANG |
| No Progress | 4/24/2025 | ANTHONY EGSON |
| CofO in Progress | 4/24/2025 | ANTHONY EGSON |
| Permit Finaled | 12/31/2025 | ANSON MAGLASANG |
| CofO Issued | 12/31/2025 | ANSON MAGLASANG |
| Permit Finaled | 12/31/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2023 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 8/24/2023 | CINDY QI |
| ZI | Cleared | 8/24/2023 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 8/29/2023 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/19/2023 | Approved | JOHN KLARIN |
| Pre-Inspection | 10/19/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/6/2023 | Not Ready for Inspection | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Partial Inspection | JOHN KLARIN |
| Green Building Rough | 11/6/2023 | Not Ready for Inspection | JOHN KLARIN |
| Pre-Inspection | 12/13/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 1/26/2024 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Corrections Issued | JAMES CHAVEZ |
| Gas Test | 1/26/2024 | Partial Approval | JAMES CHAVEZ |
| HVAC-Rough | 1/26/2024 | Corrections Issued | JAMES CHAVEZ |
| PLUMBING-Rough | 1/26/2024 | Approved | JAMES CHAVEZ |
| Deputy Wood Construction | 1/29/2024 | Conditional Approval | JAMES CHAVEZ |
| Wood Frame | 2/6/2024 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Rough | 2/8/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 2/8/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 2/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 2/14/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Green Building Rough | 2/14/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Rough | 2/14/2024 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Rough | 2/22/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 2/22/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 2/27/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 2/27/2024 | Approved | BEN MOLSTAD |
| Shower Pan | 3/1/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Wood Frame | 3/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Partial Approval | BEN MOLSTAD |
| Shower Pan | 3/7/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Shower Pan | 3/18/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 3/21/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 3/22/2024 | Conditional Approval | BEN MOLSTAD |
| Green Building Rough | 3/22/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 4/2/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 4/12/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| Drywall Nailing | 4/15/2024 | Approved | BEN MOLSTAD |
| Rough-Elec/Plmb/HVAC | 5/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Underground Mechanical | 5/8/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 5/31/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 5/31/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 5/31/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 5/31/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 5/31/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 5/31/2024 | Approved | BEN MOLSTAD |
| HVAC-Final | 5/31/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 5/31/2024 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 5/31/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 6/5/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 6/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 6/5/2024 | Approved | BEN MOLSTAD |
| Final | 6/12/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 6/12/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 6/12/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Final | 7/10/2024 | OK to Issue CofO | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | BEN MOLSTAD |