8417 S WINSFORD AVE 90045

Certificate Information: 8417 S WINSFORD AVE 90045

Application / Permit
23014-30000-03120
Plan Check / Job No.
B23WL01991
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 63 SQ FT OF RFA and Remodel TO EXISTING SINGLE STORY 1458 SF SFD ---1 OF 2---
Permit Issued
Issued on 6/3/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2023 APPLICANT
Assigned to Plan Check Engineer 8/9/2023 YASHAR EMAMI
Corrections Issued 8/17/2023 YASHAR EMAMI
Quality Review Completed 8/28/2023 KAVIAN REFAHI
Building Plans Picked Up 8/29/2023 APPLICANT
Applicant returned to address corrections 3/27/2024 YASHAR EMAMI
Applicant returned to address corrections 4/19/2024 YASHAR EMAMI
Plan Check Approved 4/30/2024 YASHAR EMAMI
Issued 6/3/2024 APPLICANT
CofO in Progress 7/2/2025 MICHAEL ALLEN
Permit Finaled 7/9/2025 RICHARD STEINBACH
Permit Finaled 7/9/2025 RICHARD STEINBACH
CofO Issued 7/9/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/8/2024 DINAH GARIN
GPI Written Notices Cleared 4/19/2024 YASHAR EMAMI
Grading Pre-Inspection Cleared 4/19/2024 YASHAR EMAMI
Eng Process Fee Ord 176,300 Cleared 4/24/2024 DINAH GARIN

Contact Information

Contractor Bless It Construction Inc; Lic. No.: 1048746-B 1824 E KAY STREET      COMPTON, CA 90221
Engineer Padilla,, Joseph G; Lic. No.: C72117 1553 PICASSO LN      OXNARD, CA 93033

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/18/2024 Corrections Issued BOBBY KEY
Deputy Reinf. Concrete 6/20/2024 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Partial Approval JESUS PINEDA
Green Building Rough 7/3/2024 Not Ready for Inspection JESUS PINEDA
PLUMBING-Rough 7/3/2024 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/8/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 7/8/2024 Approved JESUS PINEDA
Deputy Wood Construction 7/15/2024 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 7/15/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Conditional Approval BOBBY KEY
HVAC-Rough 7/15/2024 Approved BOBBY KEY
PLUMBING-Rough 7/15/2024 Approved BOBBY KEY
BUILDING-Rough-Frame 8/16/2024 Approved BOBBY KEY
Green Building Rough 8/16/2024 Approved BOBBY KEY
Insulation 8/16/2024 Approved BOBBY KEY
Interior/Exterior Lathing 8/16/2024 Partial Approval BOBBY KEY
Shower Pan 8/16/2024 Approved BOBBY KEY
Drywall Nailing 8/20/2024 Approved BOBBY KEY
Interior/Exterior Lathing 8/20/2024 Approved BOBBY KEY
ELECTRICAL-Final 1/28/2025 Corrections Issued BOBBY KEY
Final 1/28/2025 Corrections Issued BOBBY KEY
Green Building Final 1/28/2025 Approved BOBBY KEY
HVAC-Final 1/28/2025 Approved BOBBY KEY
PLUMBING-Final 1/28/2025 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Not Ready BOBBY KEY
Smoke Detectors 1/28/2025 Approved BOBBY KEY
Final 4/29/2025 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 4/29/2025 SGSOV Not Ready JESUS PINEDA
Service/Power Release 4/29/2025 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Final 6/25/2025 Approved BOBBY KEY
Final 6/25/2025 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Approved BOBBY KEY
Final 7/1/2025 OK to Issue CofO MICHAEL ALLEN
Service/Power Release 7/1/2025 Approved MICHAEL ALLEN