1527 W 36TH PL 90018
Certificate Information: 1527 W 36TH PL 90018
- Application / Permit
- 23014-30000-03019
- Plan Check / Job No.
- B23WL01921
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Remove portion of (E) detached garage in the rear of the lot with a ground floor addition and a (N) second story to be used entirely as an ADU per LAMC 12.22 A.33 (c) & (d).
- Permit Issued
- Issued on 2/21/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/21/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2023 | JAHANSHAH POURHASSAN |
| Corrections Issued | 8/3/2023 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 8/11/2023 | APPLICANT |
| Applicant returned to address corrections | 9/26/2024 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 10/29/2024 | JAHANSHAH POURHASSAN |
| Issued | 2/21/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2023 | ARNULFO CHAMU |
| Roof/Waste drainage to street | Cleared | 11/14/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2023 | ARNULFO CHAMU |
| Sewer availability | Cleared | 11/15/2023 | ARNULFO CHAMU |
| Hydrant and Access approval | Cleared | 11/25/2023 | RUEL COLE |
| Low Impact Development (LID) | Cleared | 8/30/2024 | DEBORA LEITE |
| Community Plan Implem. Overlay | Cleared | 2/13/2025 | MANERI ROMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 4/14/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/14/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 5/19/2025 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Approved | SABAS ALONSO |
| Gas Test | 7/31/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 7/31/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 7/31/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 7/31/2025 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 8/7/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 8/7/2025 | Approved | SABAS ALONSO |
| Shower Pan | 8/7/2025 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/21/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 8/21/2025 | Approved | BRENDAN MORELLI |
| Shower Pan | 8/21/2025 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 9/25/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/25/2025 | Corrections Issued | SABAS ALONSO |
| Sewer | 9/25/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 9/25/2025 | Approved | SABAS ALONSO |
| Insulation | 10/8/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 10/8/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 10/30/2025 | Approved | SABAS ALONSO |