6426 W QUEBEC DR 90068

Certificate Information: 6426 W QUEBEC DR 90068

Application / Permit
23014-30000-03004
Plan Check / Job No.
B23WL01916
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to, and partial remodel of existing S.F.D. by convert (E) crawl space
Permit Issued
Issued on 10/16/2024
Issuing Office
Valley
Current Status
Issued on 10/16/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/27/2023 APPLICANT
Assigned to Plan Check Engineer 8/9/2023 HOOMAN HAJIZADEH
Corrections Issued 8/15/2023 HOOMAN HAJIZADEH
Quality Review Completed 8/24/2023 CHIHARU SUZUKI
Building Plans Picked Up 8/25/2023 APPLICANT
Applicant returned to address corrections 9/6/2023 HOOMAN HAJIZADEH
Applicant returned to address corrections 10/18/2023 HOOMAN HAJIZADEH
Applicant returned to address corrections 2/5/2024 HOOMAN HAJIZADEH
Applicant returned to address corrections 2/14/2024 HOOMAN HAJIZADEH
Plan Check Approved 3/6/2024 HOOMAN HAJIZADEH
Issued 10/16/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/16/2024 JEANIE LAM
Sewer availability Cleared 1/24/2024 JEANIE LAM
Hydrant and Access approval Cleared 2/17/2024 JOHN CONNEALLY
Grading Pre-Inspection Cleared 3/6/2024 HOOMAN HAJIZADEH

Contact Information

Architect Rees,, Robert S; Lic. No.: C26934 3483 BARRY AVENUE      LOS ANGELES, CA 90066
Contractor Mackey And Son Inc; Lic. No.: 790087-B 10945 DARBY AVENUE      PORTER RANCH, CA 91326
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Engineer Payan,, Atanacio; Lic. No.: L7796 2404 MARY CLARE ST      CORONA, CA 92882
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801
Geologist Triebold,, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 12/12/2024 Partial Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 12/18/2024 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 1/15/2025 Not Ready for Inspection BRENDAN MORELLI
Piling/Pier/Caisson 1/15/2025 Corrections Issued BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 1/22/2025 Partial Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 1/23/2025 Conditional Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 2/6/2025 Conditional Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 3/6/2025 Conditional Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 3/13/2025 Conditional Approval CRAIG VAUGHAN
Deputy Reinf. Concrete 3/18/2025 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 3/20/2025 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 4/10/2025 Approved CRAIG VAUGHAN
Deputy Steel/Welding 8/12/2025 Conditional Approval CRAIG VAUGHAN
Deputy Steel/Welding 8/13/2025 Conditional Approval CRAIG VAUGHAN
Wood Frame 9/24/2025 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 10/2/2025 Conditional Approval CRAIG VAUGHAN
Wood Frame 2/18/2026 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Rough 2/27/2026 Partial Approval CRAIG VAUGHAN
HVAC-Rough 2/27/2026 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 2/27/2026 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 4/2/2026 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Rough 4/2/2026 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 4/2/2026 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 4/2/2026 Approved CRAIG VAUGHAN
Insulation 4/27/2026 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 4/27/2026 Partial Approval CRAIG VAUGHAN