2102 S GREENFIELD AVE 90025
Certificate Information: 2102 S GREENFIELD AVE 90025
- Application / Permit
- 23014-30000-02861
- Plan Check / Job No.
- B23WL01834
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition of 7'-1" x 20'-4" at the side of first floor of (E) S.F.D. "COMPLY WITH DEPARTMENT ORDER effective date 08/04/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 10/6/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO in Progress on 5/30/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2023 | CAROLEAN BASMA |
| Corrections Issued | 7/18/2023 | CAROLEAN BASMA |
| Applicant returned to address corrections | 9/20/2023 | CAROLEAN BASMA |
| Applicant returned to address corrections | 9/22/2023 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 9/28/2023 | JAHANSHAH POURHASSAN |
| Issued | 10/6/2023 | APPLICANT |
| CofO in Progress | 5/30/2024 | RUBEN PEREZ |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/11/2023 | SERGIO VALENZUELA |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2023 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 9/13/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 9/13/2023 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mah,, Edwin Poy-Dor; Lic. No.: C27141 | 1740 APPIAN WAY MONTEBELLO, CA 90640 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/14/2023 | Not Ready for Inspection | PETER RUBIO |
| Footing/Foundation/Slab | 12/14/2023 | Not Ready for Inspection | PETER RUBIO |
| Green Building Rough | 12/14/2023 | Not Ready for Inspection | PETER RUBIO |
| Footing/Foundation/Slab | 12/19/2023 | Approved | PETER RUBIO |
| Deputy Drilled-In Anchors | 12/20/2023 | Approved | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2024 | Approved | PETER RUBIO |
| Green Building Rough | 1/5/2024 | Not Ready for Inspection | PETER RUBIO |
| BUILDING-Rough-Frame | 2/7/2024 | Not Ready for Inspection | PETER RUBIO |
| ELECTRICAL-Rough | 2/7/2024 | Not Ready for Inspection | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2024 | Not Ready for Inspection | PETER RUBIO |
| Green Building Rough | 2/7/2024 | Not Ready for Inspection | PETER RUBIO |
| PLUMBING-Rough | 2/7/2024 | Not Ready for Inspection | PETER RUBIO |
| BUILDING-Rough-Frame | 2/21/2024 | Approved | PETER RUBIO |
| Green Building Rough | 2/21/2024 | Approved | PETER RUBIO |
| ELECTRICAL-Rough | 3/12/2024 | Approved | PETER RUBIO |
| Insulation | 3/12/2024 | Approved | PETER RUBIO |
| Interior/Exterior Lathing | 3/12/2024 | Approved | PETER RUBIO |
| PLUMBING-Rough | 3/12/2024 | Not Ready for Inspection | PETER RUBIO |
| PLUMBING-Rough | 3/18/2024 | Approved | RUBEN PEREZ |
| Drywall Nailing | 4/3/2024 | Approved | PETER RUBIO |
| Interior/Exterior Lathing | 4/10/2024 | Approved | EMIL OPFFER |
| Final | 5/16/2024 | Corrections Issued | RUBEN PEREZ |
| Green Building Final | 5/16/2024 | Approved | RUBEN PEREZ |
| SGSOV-Seismic Gas S/O Valve | 5/16/2024 | SGSOV Approved | RUBEN PEREZ |
| Smoke Detectors | 5/16/2024 | Approved | RUBEN PEREZ |
| Final | 5/29/2024 | OK to Issue CofO | RUBEN PEREZ |