2102 S GREENFIELD AVE 90025

Certificate Information: 2102 S GREENFIELD AVE 90025

Application / Permit
23014-30000-02861
Plan Check / Job No.
B23WL01834
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition of 7'-1" x 20'-4" at the side of first floor of (E) S.F.D. "COMPLY WITH DEPARTMENT ORDER effective date 08/04/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 10/6/2023
Issuing Office
West Los Angeles
Current Status
CofO in Progress on 5/30/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/18/2023 APPLICANT
Assigned to Plan Check Engineer 7/18/2023 CAROLEAN BASMA
Corrections Issued 7/18/2023 CAROLEAN BASMA
Applicant returned to address corrections 9/20/2023 CAROLEAN BASMA
Applicant returned to address corrections 9/22/2023 JAHANSHAH POURHASSAN
Plan Check Approved 9/28/2023 JAHANSHAH POURHASSAN
Issued 10/6/2023 APPLICANT
CofO in Progress 5/30/2024 RUBEN PEREZ

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/11/2023 SERGIO VALENZUELA
Eng Process Fee Ord 176,300 Cleared 9/13/2023 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 9/13/2023 ANTHONY MAINEZ
Sewer availability Cleared 9/13/2023 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mah,, Edwin Poy-Dor; Lic. No.: C27141 1740 APPIAN WAY      MONTEBELLO, CA 90640

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/14/2023 Not Ready for Inspection PETER RUBIO
Footing/Foundation/Slab 12/14/2023 Not Ready for Inspection PETER RUBIO
Green Building Rough 12/14/2023 Not Ready for Inspection PETER RUBIO
Footing/Foundation/Slab 12/19/2023 Approved PETER RUBIO
Deputy Drilled-In Anchors 12/20/2023 Approved PETER RUBIO
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Approved PETER RUBIO
Green Building Rough 1/5/2024 Not Ready for Inspection PETER RUBIO
BUILDING-Rough-Frame 2/7/2024 Not Ready for Inspection PETER RUBIO
ELECTRICAL-Rough 2/7/2024 Not Ready for Inspection PETER RUBIO
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Not Ready for Inspection PETER RUBIO
Green Building Rough 2/7/2024 Not Ready for Inspection PETER RUBIO
PLUMBING-Rough 2/7/2024 Not Ready for Inspection PETER RUBIO
BUILDING-Rough-Frame 2/21/2024 Approved PETER RUBIO
Green Building Rough 2/21/2024 Approved PETER RUBIO
ELECTRICAL-Rough 3/12/2024 Approved PETER RUBIO
Insulation 3/12/2024 Approved PETER RUBIO
Interior/Exterior Lathing 3/12/2024 Approved PETER RUBIO
PLUMBING-Rough 3/12/2024 Not Ready for Inspection PETER RUBIO
PLUMBING-Rough 3/18/2024 Approved RUBEN PEREZ
Drywall Nailing 4/3/2024 Approved PETER RUBIO
Interior/Exterior Lathing 4/10/2024 Approved EMIL OPFFER
Final 5/16/2024 Corrections Issued RUBEN PEREZ
Green Building Final 5/16/2024 Approved RUBEN PEREZ
SGSOV-Seismic Gas S/O Valve 5/16/2024 SGSOV Approved RUBEN PEREZ
Smoke Detectors 5/16/2024 Approved RUBEN PEREZ
Final 5/29/2024 OK to Issue CofO RUBEN PEREZ