903-903 1/2 E 43RD ST 90011
Certificate Information: 903-903 1/2 E 43RD ST 90011
- Application / Permit
- 23014-30000-02641
- Plan Check / Job No.
- B23WL01724
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ATACH ADU CONVERSION PER ORDINACE LAMC 12.22 A.33(c) NEW TRELLIS
- Permit Issued
- Issued on 3/28/2024
- Issuing Office
- Metro
- Current Status
- Issued on 3/28/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2023 | YASHAR EMAMI |
| Corrections Issued | 8/21/2023 | YASHAR EMAMI |
| Quality Review Completed | 8/29/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 8/31/2023 | APPLICANT |
| Plan Check Approved | 3/21/2024 | YASHAR EMAMI |
| Issued | 3/28/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/5/2023 | WALLIE JONG |
| Sewer availability | Cleared | 9/5/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2023 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 3/13/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 3/13/2024 | JUSTIN BICOL |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 11/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 12/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 12/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 12/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 12/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 12/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 12/30/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/30/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 1/14/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 1/28/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 1/28/2025 | Partial Approval | ALEJANDRO DE ARTOLA |