2321 N WESTRIDGE ROAD 90049
Certificate Information: 2321 N WESTRIDGE ROAD 90049
- Application / Permit
- 23014-30000-02398
- Plan Check / Job No.
- B23WL01580
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- addition / remodel to a (e) 2-story S.F.D. w/ attached garage. (n) addtiions to 1st & 2nd floor. build new trellis at front of residence w/ steel post & beams
- Permit Issued
- Issued on 1/24/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/24/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2023 | KAVIAN REFAHI |
| Corrections Issued | 6/25/2023 | KAVIAN REFAHI |
| Quality Review Completed | 6/28/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 6/29/2023 | APPLICANT |
| Plan Check Approved | 1/24/2024 | KAVIAN REFAHI |
| Issued | 1/24/2024 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 12/12/2023 | SAMUEL LINN |
| BHO/Hillside ordinance | Cleared | 12/18/2023 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 12/18/2023 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 12/18/2023 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 12/18/2023 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 12/18/2023 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2023 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 12/18/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/18/2023 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 1/24/2024 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 1/24/2024 | KAVIAN REFAHI |
Contact Information
| Contractor | Stregan Group Ltd; Lic. No.: 962579-B | 5739 KANAN RD #255 AGOURA HILLS, CA 91301 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/23/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 6/25/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/1/2025 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/18/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 8/18/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 8/18/2025 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 8/18/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/18/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 8/18/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 8/20/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 8/20/2025 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 8/26/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/26/2025 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 8/28/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/28/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 9/10/2025 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 9/10/2025 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 9/24/2025 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 9/24/2025 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 11/25/2025 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 1/9/2026 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 1/9/2026 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 1/9/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 1/13/2026 | Approved | KEVIN SARGSYAN |
| Insulation | 1/22/2026 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 2/11/2026 | Approved | KEVIN SARGSYAN |
| Shower Pan | 2/11/2026 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/19/2026 | Approved | KEVIN SARGSYAN |