13200 W LAKE ST 90066
Certificate Information: 13200 W LAKE ST 90066
- Application / Permit
- 23014-30000-02361
- Plan Check / Job No.
- B23WL01570
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2-story addition to (e) single story SFD with attached 2-car garage
- Permit Issued
- Issued on 9/20/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2023 | REZA HAGHIGHAT |
| Corrections Issued | 6/17/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 6/26/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 7/5/2023 | APPLICANT |
| Plan Check Approved | 9/14/2023 | REZA HAGHIGHAT |
| Issued | 9/20/2023 | APPLICANT |
| CofO in Progress | 8/30/2024 | JESUS PINEDA |
| Permit Finaled | 9/3/2024 | RICHARD STEINBACH |
| CofO Issued | 9/3/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/3/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2023 | JASON NG |
| Permit | Cleared | 7/24/2023 | JASON NG |
| Sewer availability | Cleared | 7/24/2023 | JASON NG |
| Trees in Parkway | Cleared | 8/15/2023 | ADALBERTO VERA |
| Low Impact Development (LID) | Cleared | 8/31/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 9/5/2023 | DARIN LAM |
| GPI Written Notices | Cleared | 9/14/2023 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 9/14/2023 | REZA HAGHIGHAT |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Rivera Jason; Lic. No.: 1078296-C20 | P O BOX 628 THERMAL, CA 92274 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/27/2023 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 11/1/2023 | Partial Approval | HERBERT GIRON |
| Deputy Drilled-In Anchors | 11/6/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 11/7/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 11/7/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2024 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/6/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 2/6/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 2/6/2024 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/15/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/15/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 2/15/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 2/15/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/15/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/15/2024 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 2/15/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 2/21/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 2/26/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/27/2024 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 3/27/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 8/26/2024 | Corrections Issued | JESUS PINEDA |
| Gas Test | 8/26/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 8/26/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 8/26/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 8/29/2024 | Approved | JESUS PINEDA |
| Final | 8/29/2024 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 8/29/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 8/29/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 8/29/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/29/2024 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 8/29/2024 | Approved | JESUS PINEDA |
| Smoke Detectors | 8/29/2024 | Approved | JESUS PINEDA |