4245 S GRAND VIEW BLVD 90066

Certificate Information: 4245 S GRAND VIEW BLVD 90066

Application / Permit
23014-30000-02289
Plan Check / Job No.
B23WL01518
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition to (e) single story SFD, add an att. 1-car garage
Permit Issued
Issued on 10/23/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2023 APPLICANT
Assigned to Plan Check Engineer 6/15/2023 REZA HAGHIGHAT
Corrections Issued 6/18/2023 REZA HAGHIGHAT
Quality Review Completed 6/26/2023 KAVIAN REFAHI
Building Plans Picked Up 6/29/2023 APPLICANT
Plan Check Approved 10/23/2023 REZA HAGHIGHAT
Issued 10/23/2023 APPLICANT
CofO in Progress 4/22/2025 MICHAEL ALLEN
Permit Finaled 4/22/2025 RICHARD STEINBACH
CofO Issued 4/22/2025 RICHARD STEINBACH
Permit Finaled 4/22/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 7/10/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 7/11/2023 JASON NG
Low Impact Development (LID) Cleared 10/3/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 10/4/2023 BRENDEN HAWK

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/13/2023 Partial Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 1/22/2024 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/25/2024 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 1/25/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/18/2024 Partial Approval TEMISTOCLES CAAL
Deputy Wood Construction 3/19/2024 Conditional Approval JESUS RODRIGUEZ
Underground Mechanical 3/26/2024 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/24/2024 Partial Approval JESUS RODRIGUEZ
HVAC-Rough 5/29/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 7/22/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 7/22/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 8/6/2024 Approved JESUS RODRIGUEZ
Green Building Rough 8/6/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/6/2024 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 8/6/2024 Approved JESUS RODRIGUEZ
Shower Pan 8/20/2024 Approved JESUS RODRIGUEZ
Insulation 9/4/2024 Corrections Issued BOBBY KEY
Drywall Nailing 9/23/2024 Approved JESUS PINEDA
Insulation 9/23/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 10/4/2024 Not Ready for Inspection MICHAEL ALLEN
Interior/Exterior Lathing 10/7/2024 Approved REGINA MENDEZ
ELECTRICAL-Final 3/3/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 3/3/2025 Approved JESUS PINEDA
HVAC-Final 3/19/2025 Corrections Issued MICHAEL ALLEN
ELECTRICAL-Final 3/27/2025 Corrections Issued MICHAEL ALLEN
HVAC-Final 3/27/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 4/2/2025 Approved MICHAEL ALLEN
Final 4/4/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 4/4/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 4/4/2025 Approved MICHAEL ALLEN
Final 4/21/2025 OK to Issue CofO MICHAEL ALLEN