743 E SUNSET AVE 90291

Certificate Information: 743 E SUNSET AVE 90291

Application / Permit
23014-30000-02229
Plan Check / Job No.
B23WL01486
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 STORY 450 SQ FT ADDITION TO (E) 1 STORY SFD IN VENICE SPECIFIC PLAN PER ENGINEERS CALCS
Permit Issued
Issued on 1/3/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2023 APPLICANT
Assigned to Plan Check Engineer 6/7/2023 YASHAR EMAMI
Corrections Issued 6/16/2023 YASHAR EMAMI
Quality Review Completed 6/27/2023 KAVIAN REFAHI
Building Plans Picked Up 6/29/2023 APPLICANT
Plan Check Approved 11/28/2023 YASHAR EMAMI
Issued 1/3/2024 APPLICANT
CofO in Progress 12/3/2024 BOBBY KEY
Permit Finaled 12/3/2024 RICHARD STEINBACH
CofO Issued 12/3/2024 RICHARD STEINBACH
Permit Finaled 12/3/2024 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/11/2023 JASON NG
Miscellaneous Cleared 7/14/2023 NOAH MCCOY
ZA Case Cleared 7/14/2023 NOAH MCCOY
ZA Case Cleared 7/14/2023 NOAH MCCOY
ZA Case Cleared 7/14/2023 NOAH MCCOY
ZA Case Cleared 7/14/2023 NOAH MCCOY
Eng Process Fee Ord 176,300 Cleared 7/24/2023 JASON NG
Coastal Zone Cleared 9/19/2023 JAZMIN ROQUE
Frnt yard landscape/Water mgmt Cleared 9/19/2023 JAZMIN ROQUE
Specific Plan Cleared 10/3/2023 LUIS LOPEZ

Contact Information

Contractor Cornejo Construction Inc; Lic. No.: 967300-B 1558 E 111TH ST      LOS ANGELES, CA 90059
Engineer Bayani-Rad,, Padra; Lic. No.: C86320 15901 HAWTHORNE BLVD UNIT 220      LAWNDALE, CA 90260

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/27/2024 Partial Approval HERBERT GIRON
Deputy Drilled-In Anchors 3/4/2024 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 3/5/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 3/19/2024 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 3/21/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 3/28/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 4/8/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 5/23/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval HERBERT GIRON
HVAC-Rough 5/23/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 5/23/2024 Approved HERBERT GIRON
ELECTRICAL-Rough 6/6/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 6/6/2024 Approved HERBERT GIRON
Deputy Drilled-In Anchors 6/14/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 6/26/2024 Approved HERBERT GIRON
Green Building Rough 6/26/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 6/26/2024 Partial Approval HERBERT GIRON
Insulation 7/5/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/5/2024 Partial Approval ARAM AVEDISIAN
Shower Pan 7/5/2024 Approved ARAM AVEDISIAN
Drywall Nailing 7/10/2024 Approved HERBERT GIRON
ELECTRICAL-Final 10/21/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 10/21/2024 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 10/21/2024 Approved HERBERT GIRON
ELECTRICAL-Final 12/2/2024 Approved BOBBY KEY
Final 12/2/2024 OK to Issue CofO BOBBY KEY
Green Building Final 12/2/2024 Approved BOBBY KEY
HVAC-Final 12/2/2024 Approved BOBBY KEY
PLUMBING-Final 12/2/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Approved BOBBY KEY