4418 S GRAND VIEW BLVD 90066

Certificate Information: 4418 S GRAND VIEW BLVD 90066

Application / Permit
23014-30000-01998
Plan Check / Job No.
B23WL01351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2nd floor ADU (825 sf) addition to (e) detached garage and workshop (storage) per LAMC 12.22 A.33(c) AND (d) with new patio cover at 1st floor
Permit Issued
Issued on 8/22/2024
Issuing Office
West Los Angeles
Current Status
Issued on 8/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/19/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 REZA HAGHIGHAT
Corrections Issued 5/29/2023 REZA HAGHIGHAT
Quality Review Completed 6/6/2023 KAVIAN REFAHI
Building Plans Picked Up 6/7/2023 APPLICANT
Applicant returned to address corrections 7/24/2024 REZA HAGHIGHAT
Plan Check Approved 8/16/2024 REZA HAGHIGHAT
Issued 8/22/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/31/2023 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 9/6/2023 JASON NG
Sewer availability Cleared 9/6/2023 JASON NG
Hydrant and Access approval Cleared 9/24/2023 JOHN CONNEALLY
Specific Plan Cleared 10/10/2023 ALESSANDRO MERCURI
Construction near power lines Cleared 11/8/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 6/24/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/9/2024 ANDREA SAINT-ANTONIN

Contact Information

Contractor Owner-Builder       ,
Engineer Cattan,, Christian George; Lic. No.: C82566 8444 OWENSMOUTH AVE      CANOGA PARK, CA 91304

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/18/2024 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 10/18/2024 Partial Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 11/21/2024 Partial Approval JESUS PINEDA
Special/Order Compliance 11/21/2024 Corrections Issued JESUS PINEDA
Excavation/Setback/Form/Re-Bar 12/10/2024 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 12/10/2024 Partial Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 1/14/2025 Approved JESUS PINEDA
Footing/Foundation/Slab 1/14/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/24/2025 Corrections Issued JESUS PINEDA
Special/Order Compliance 2/24/2025 Corrections Issued JESUS PINEDA
Special/Order Compliance 3/14/2025 Partial Inspection BOBBY KEY
Deputy Wood Construction 4/9/2025 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Corrections Issued BOBBY KEY
PLUMBING-Rough 4/29/2025 Corrections Issued BOBBY KEY
Special/Order Compliance 4/29/2025 Partial Inspection BOBBY KEY
HVAC-Rough 6/6/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 6/6/2025 Partial Approval RUBEN RIVAS
PLUMBING-Rough 6/6/2025 Approved RUBEN RIVAS
ELECTRICAL-Rough 6/11/2025 Approved MICHAEL ALLEN
Special/Order Compliance 6/11/2025 Corrections Issued MICHAEL ALLEN
Underground Mechanical 6/11/2025 Approved MICHAEL ALLEN
BUILDING-Rough-Frame 6/12/2025 Corrections Issued MICHAEL ALLEN
Green Building Rough 6/12/2025 Approved MICHAEL ALLEN
Special/Order Compliance 6/12/2025 Partial Approval MICHAEL ALLEN
Special/Order Compliance 7/16/2025 Partial Inspection JUAN VALENZUELA
Insulation 8/27/2025 Not Ready for Inspection WILBER ROSALES
BUILDING-Rough-Frame 10/8/2025 Approved WILBER ROSALES
Drywall Nailing 10/8/2025 Approved WILBER ROSALES
Insulation 10/8/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 10/15/2025 Approved WILBER ROSALES
Shower Pan 10/15/2025 Approved WILBER ROSALES