1920 S BAGLEY AVE 90035

Certificate Information: 1920 S BAGLEY AVE 90035

Application / Permit
23014-30000-01977
Plan Check / Job No.
B23WL01333
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition and remodel to (e) 2-story S.F.D. w/ att. 2-car garage, work include kitchen & bathroom remodel & reconfigure 1st floor & enclose existing 2nd floor balcony
Permit Issued
Issued on 12/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/31/2023 REZA HAGHIGHAT
Corrections Issued 6/4/2023 REZA HAGHIGHAT
Quality Review Completed 6/8/2023 KAVIAN REFAHI
Building Plans Picked Up 7/5/2023 APPLICANT
Plan Check Approved 10/11/2023 REZA HAGHIGHAT
Issued 12/18/2023 APPLICANT
CofO in Progress 11/19/2025 ASHLEY THOMPSON
Permit Finaled 11/29/2025 RICHARD STEINBACH
CofO Issued 11/29/2025 RICHARD STEINBACH
Permit Finaled 11/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/10/2023 JASON NG
Sewer availability Cleared 7/10/2023 JASON NG
Construction near power lines Cleared 8/21/2023 RIDWAN HARDY
Roof/Waste drainage to street Cleared 9/30/2023 DARIN LAM
Grading Pre-Inspection Cleared 10/11/2023 REZA HAGHIGHAT

Contact Information

Architect Langer-Voss,, Naomi; Lic. No.: C32512 210 W 101ST ST #4L      NEW YORK, NY 10025
Contractor Nittay Inc; Lic. No.: 1033506-B 17941 VENTURA BLVD #204      ENCINO, CA 91316
Engineer Lotfi,, Fariborz F; Lic. No.: C49359 1328 DUENDE LANE      PACIFIC PALISADES, CA 90272

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/30/2024 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 1/30/2024 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 1/30/2024 Partial Approval OGANES TARAKHCHYAN
METHANE-Barrier 1/30/2024 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 2/23/2024 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 3/1/2024 Partial Approval OGANES TARAKHCHYAN
METHANE-Barrier 3/1/2024 Approved OGANES TARAKHCHYAN
METHANE-Subgrade 3/1/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 3/1/2024 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 4/1/2024 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 4/3/2024 Approved OGANES TARAKHCHYAN
Shower Pan 4/9/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/12/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/2/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 5/7/2024 Approved OGANES TARAKHCHYAN
Wood Frame 5/7/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/13/2024 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/16/2024 Partial Approval MEL KHACHATOURIAN
Interior/Exterior Lathing 5/21/2024 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 6/25/2024 No Access for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 6/27/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 7/11/2024 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 7/15/2024 Corrections Issued STEPHANIE SWANSON
Green Building Rough 7/15/2024 Not Ready for Inspection STEPHANIE SWANSON
Insulation 7/15/2024 Not Ready for Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 7/17/2024 Corrections Issued SEAN HAUPT
Insulation 7/17/2024 Not Ready for Inspection SEAN HAUPT
Insulation 7/23/2024 Partial Approval KENNETH NAGLE
Drywall Nailing 7/29/2024 Corrections Issued ASHLEY THOMPSON
Green Building Rough 7/29/2024 Not Ready for Inspection ASHLEY THOMPSON
Special/Order Compliance 7/29/2024 Partial Approval REGINA MENDEZ
Drywall Nailing 8/1/2024 Partial Approval ASHLEY THOMPSON
Green Building Rough 8/1/2024 Not Ready for Inspection ASHLEY THOMPSON
BUILDING-Rough-Frame 2/3/2025 Approved EVAN COOPER
Drywall Nailing 2/3/2025 Approved EVAN COOPER
Final 2/3/2025 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 2/3/2025 Approved EVAN COOPER
Green Building Final 2/3/2025 Approved EVAN COOPER
Green Building Rough 2/3/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/3/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 2/3/2025 Approved EVAN COOPER
Final 11/19/2025 OK to Issue CofO ASHLEY THOMPSON