3097 S MANNING AVE 90064
Certificate Information: 3097 S MANNING AVE 90064
- Application / Permit
- 23014-30000-01947
- Plan Check / Job No.
- B23WL01306
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition (282 sf) and conversion of (e) attached 2-car garage (457 sf) to (e) 2-story SFD (1,712 sf) to an ADU per LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 6/20/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO in Progress on 7/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | REZA HAGHIGHAT |
| Corrections Issued | 5/29/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 6/6/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 6/8/2023 | APPLICANT |
| Plan Check Approved | 6/20/2023 | REZA HAGHIGHAT |
| Issued | 6/20/2023 | APPLICANT |
| CofO in Progress | 7/25/2025 | RUBEN PEREZ |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2023 | DINAH GARIN |
| Sewer availability | Cleared | 6/2/2023 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 6/5/2023 | LIAM ODONOVAN |
| Specific Plan | Cleared | 6/5/2023 | ALESSANDRO MERCURI |
| ZA Case | Cleared | 6/5/2023 | LOUIS ORTEGA |
| Grading Pre-Inspection | Cleared | 6/20/2023 | REZA HAGHIGHAT |
Contact Information
| Contractor | Eurocon Group Inc; Lic. No.: 708010-B | 923 HILTS AVE LOS ANGELES, CA 90024 |
| Engineer | Farag,, Amgad N; Lic. No.: C74076 | 27050 MAPLE TREE CT VALENCIA, CA 91381 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/8/2024 | Partial Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 8/23/2024 | Approved | PETER RUBIO |
| BUILDING-Rough-Frame | 10/4/2024 | Not Ready for Inspection | PETER RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Approved | PETER RUBIO |
| MERV13>=Rough | 10/4/2024 | Not Ready for Inspection | PETER RUBIO |
| PLUMBING-Rough | 10/15/2024 | Approved | RUBEN PEREZ |
| ELECTRICAL-Rough | 10/24/2024 | Approved | PETER RUBIO |
| BUILDING-Rough-Frame | 10/29/2024 | Approved | PETER RUBIO |
| Green Building Rough | 10/29/2024 | Approved | PETER RUBIO |
| HVAC-Rough | 10/29/2024 | Approved | PETER RUBIO |
| MERV13>=Rough | 10/29/2024 | Approved | PETER RUBIO |
| Insulation | 10/31/2024 | Approved | PETER RUBIO |
| Interior/Exterior Lathing | 11/7/2024 | Partial Inspection | ROBERT CHAVEZ |
| Drywall Nailing | 11/13/2024 | Approved | PETER RUBIO |
| Shower Pan | 11/13/2024 | Not Ready for Inspection | PETER RUBIO |
| Shower Pan | 11/20/2024 | Approved | RUBEN PEREZ |
| Final | 2/28/2025 | Corrections Issued | PETER RUBIO |
| Gas Test | 2/28/2025 | Approved | PETER RUBIO |
| Green Building Final | 2/28/2025 | Not Ready for Inspection | PETER RUBIO |
| MERV13>=Final | 2/28/2025 | Approved | PETER RUBIO |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Gas Company | PETER RUBIO |
| Smoke Detectors | 2/28/2025 | Approved | PETER RUBIO |
| Final | 6/2/2025 | Corrections Issued | PETER RUBIO |
| Green Building Final | 6/2/2025 | Not Ready for Inspection | PETER RUBIO |
| Final | 7/11/2025 | Corrections Issued | PETER RUBIO |
| Green Building Final | 7/11/2025 | Approved | PETER RUBIO |
| Final | 7/18/2025 | OK for TCO | PETER RUBIO |
| Final | 7/25/2025 | OK to Issue CofO | RUBEN PEREZ |
| Service/Power Release | 7/25/2025 | Approved | RUBEN PEREZ |