3097 S MANNING AVE 90064

Certificate Information: 3097 S MANNING AVE 90064

Application / Permit
23014-30000-01947
Plan Check / Job No.
B23WL01306
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition (282 sf) and conversion of (e) attached 2-car garage (457 sf) to (e) 2-story SFD (1,712 sf) to an ADU per LAMC 12.22 A.33(c) AND (e)
Permit Issued
Issued on 6/20/2023
Issuing Office
West Los Angeles
Current Status
CofO in Progress on 7/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/17/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 REZA HAGHIGHAT
Corrections Issued 5/29/2023 REZA HAGHIGHAT
Quality Review Completed 6/6/2023 KAVIAN REFAHI
Building Plans Picked Up 6/8/2023 APPLICANT
Plan Check Approved 6/20/2023 REZA HAGHIGHAT
Issued 6/20/2023 APPLICANT
CofO in Progress 7/25/2025 RUBEN PEREZ

Permit Application Clearance Information

Address approval Cleared 6/2/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/2/2023 DINAH GARIN
Sewer availability Cleared 6/2/2023 DINAH GARIN
Roof/Waste drainage to street Cleared 6/5/2023 LIAM ODONOVAN
Specific Plan Cleared 6/5/2023 ALESSANDRO MERCURI
ZA Case Cleared 6/5/2023 LOUIS ORTEGA
Grading Pre-Inspection Cleared 6/20/2023 REZA HAGHIGHAT

Contact Information

Contractor Eurocon Group Inc; Lic. No.: 708010-B 923 HILTS AVE      LOS ANGELES, CA 90024
Engineer Farag,, Amgad N; Lic. No.: C74076 27050 MAPLE TREE CT      VALENCIA, CA 91381

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/8/2024 Partial Inspection KIRK SANDERS
Footing/Foundation/Slab 8/23/2024 Approved PETER RUBIO
BUILDING-Rough-Frame 10/4/2024 Not Ready for Inspection PETER RUBIO
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Approved PETER RUBIO
MERV13>=Rough 10/4/2024 Not Ready for Inspection PETER RUBIO
PLUMBING-Rough 10/15/2024 Approved RUBEN PEREZ
ELECTRICAL-Rough 10/24/2024 Approved PETER RUBIO
BUILDING-Rough-Frame 10/29/2024 Approved PETER RUBIO
Green Building Rough 10/29/2024 Approved PETER RUBIO
HVAC-Rough 10/29/2024 Approved PETER RUBIO
MERV13>=Rough 10/29/2024 Approved PETER RUBIO
Insulation 10/31/2024 Approved PETER RUBIO
Interior/Exterior Lathing 11/7/2024 Partial Inspection ROBERT CHAVEZ
Drywall Nailing 11/13/2024 Approved PETER RUBIO
Shower Pan 11/13/2024 Not Ready for Inspection PETER RUBIO
Shower Pan 11/20/2024 Approved RUBEN PEREZ
Final 2/28/2025 Corrections Issued PETER RUBIO
Gas Test 2/28/2025 Approved PETER RUBIO
Green Building Final 2/28/2025 Not Ready for Inspection PETER RUBIO
MERV13>=Final 2/28/2025 Approved PETER RUBIO
SGSOV-Seismic Gas S/O Valve 2/28/2025 SGSOV Gas Company PETER RUBIO
Smoke Detectors 2/28/2025 Approved PETER RUBIO
Final 6/2/2025 Corrections Issued PETER RUBIO
Green Building Final 6/2/2025 Not Ready for Inspection PETER RUBIO
Final 7/11/2025 Corrections Issued PETER RUBIO
Green Building Final 7/11/2025 Approved PETER RUBIO
Final 7/18/2025 OK for TCO PETER RUBIO
Final 7/25/2025 OK to Issue CofO RUBEN PEREZ
Service/Power Release 7/25/2025 Approved RUBEN PEREZ