2804 N BOTTLEBRUSH DR 90077
Certificate Information: 2804 N BOTTLEBRUSH DR 90077
- Application / Permit
- 23014-30000-01899
- Plan Check / Job No.
- B23WL01274
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (35) Condo-Single Family
- Work Description
- First floor interior remodel and addition of 6'-2"x13'-1" to (E) two-story SFD.
- Permit Issued
- Issued on 10/3/2023
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 6/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2023 | JAHANSHAH POURHASSAN |
| Corrections Issued | 5/23/2023 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 5/25/2023 | APPLICANT |
| Applicant returned to address corrections | 6/22/2023 | AMY GUEVARRA |
| Plan Check Approved | 9/19/2023 | JAHANSHAH POURHASSAN |
| Issued | 10/3/2023 | APPLICANT |
| CofO in Progress | 6/8/2024 | MICHAEL PELHAM |
| Permit Finaled | 6/17/2024 | DANIEL ORRANTE |
| CofO Issued | 6/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2023 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 6/6/2023 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 6/21/2023 | SERGIO VALENZUELA |
| Specific Plan | Cleared | 9/14/2023 | JUDE HERNANDEZ |
Contact Information
| Contractor | California General Construction Llc; Lic. No.: 922027-B | 4083 CUDAHY STREET HUNTINGTON PARK, CA 90255 |
| Engineer | Mah,, Edwin Poy-Dor; Lic. No.: C27141 | 1740 APPIAN WAY MONTEBELLO, CA 90640 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/11/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/11/2023 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/31/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/31/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 1/31/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/31/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 2/23/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 2/23/2024 | Approved | SEAN HAUPT |
| HVAC-Rough | 2/23/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 2/23/2024 | Approved | SEAN HAUPT |
| Insulation | 2/27/2024 | Approved | SEAN HAUPT |
| Drywall Nailing | 3/1/2024 | Approved | SEAN HAUPT |
| Final | 6/7/2024 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 6/7/2024 | Approved | SEAN HAUPT |
| Smoke Detectors | 6/7/2024 | Approved | SEAN HAUPT |