Deputy Drilled-In Anchors
|
3/13/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
3/15/2024
|
Not Ready for Inspection
|
HAMIK HARTOUNIAN
|
|
Footing/Foundation/Slab
|
3/15/2024
|
Not Ready for Inspection
|
HAMIK HARTOUNIAN
|
|
Excavation/Setback/Form/Re-Bar
|
3/18/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/1/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
4/11/2024
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Reinf. Concrete
|
4/24/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
4/24/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Footing/Foundation/Slab
|
4/24/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
4/25/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
5/7/2024
|
Partial Approval
|
JOSEPH MCGARRY
|
|
Deputy Drilled-In Anchors
|
5/17/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
5/21/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
5/22/2024
|
Conditional Approval
|
SCOTT FINNILA
|
|
PLUMBING-Rough
|
5/31/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
6/6/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Drilled-In Anchors
|
6/17/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
6/18/2024
|
Corrections Issued
|
RICHARD DOCKUS
|
|
Excavation/Setback/Form/Re-Bar
|
6/21/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/1/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/24/2024
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
1/21/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Drilled-In Anchors
|
2/14/2025
|
Conditional Approval
|
HAMIK HARTOUNIAN
|
|
Excavation/Setback/Form/Re-Bar
|
2/18/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Reinf. Concrete
|
2/21/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Deputy Drilled-In Anchors
|
3/11/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
3/11/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Underground Mechanical
|
5/5/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Underground Mechanical
|
5/13/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/20/2025
|
Corrections Issued
|
ENRIQUE MIRELES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/1/2025
|
Partial Approval
|
ENRIQUE MIRELES
|
|
PLUMBING-Rough
|
7/25/2025
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Shower Pan
|
7/25/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Special/Order Compliance
|
7/25/2025
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
PLUMBING-Rough
|
8/22/2025
|
Approved
|
ENRIQUE MIRELES
|
|
ELECTRICAL-Rough
|
9/5/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Interior/Exterior Lathing
|
9/5/2025
|
Approved
|
ENRIQUE MIRELES
|
|
BUILDING-Rough-Frame
|
9/10/2025
|
Partial Approval
|
NICHOLAS LOPEZ
|
|
Green Building Rough
|
9/10/2025
|
Approved
|
NICHOLAS LOPEZ
|
|
HVAC-Rough
|
9/10/2025
|
Corrections Issued
|
NICHOLAS LOPEZ
|
|
Verify Sprinkler Sign Off
|
9/10/2025
|
Approved
|
NICHOLAS LOPEZ
|
|
BUILDING-Rough-Frame
|
9/15/2025
|
Approved
|
ENRIQUE MIRELES
|
|
HVAC-Rough
|
9/15/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Insulation
|
10/1/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Interior/Exterior Lathing
|
10/1/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Wood Frame
|
10/1/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Drywall Nailing
|
10/20/2025
|
Approved
|
ENRIQUE MIRELES
|
|
Underground Mechanical
|
2/17/2026
|
Not Ready for Inspection
|
ENRIQUE MIRELES
|
|
Underground Mechanical
|
2/27/2026
|
Approved
|
ENRIQUE MIRELES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/24/2026
|
Approved
|
ENRIQUE MIRELES
|
|
Insulation
|
3/24/2026
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
4/13/2026
|
Corrections Issued
|
ENRIQUE MIRELES
|
|
Drywall Nailing
|
4/21/2026
|
Approved
|
ENRIQUE MIRELES
|
|
Excavation/Setback/Form/Re-Bar
|
4/21/2026
|
Approved
|
ENRIQUE MIRELES
|