1627 1/2 W 69TH ST 90047
Certificate Information: 1627 1/2 W 69TH ST 90047
- Application / Permit
- 23014-30000-01757
- Plan Check / Job No.
- B23WL01185
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to and conversion of (E) 2 car garage into ADU per WFPP.
- Permit Issued
- Issued on 2/1/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2023 | CAROLEAN BASMA |
| Corrections Issued | 5/9/2023 | CAROLEAN BASMA |
| Building Plans Picked Up | 5/10/2023 | APPLICANT |
| Plan Check Approved | 12/20/2023 | RICHARD GARCIA |
| Issued | 2/1/2024 | APPLICANT |
| CofO Issued | 5/7/2025 | DEROLD HAUFF |
| Permit Finaled | 5/7/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2023 | HUGO LOPEZ |
| Roof/Waste drainage to street | Cleared | 6/2/2023 | HUGO LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 6/15/2023 | TREVOR QUAN |
| Construction near power lines | Cleared | 8/19/2023 | RIDWAN HARDY |
| Tenant Habitability Plan | Cleared | 12/6/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/8/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 4/12/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 4/19/2024 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 4/30/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 5/3/2024 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 5/8/2024 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 5/10/2024 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 6/27/2024 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 6/27/2024 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 8/27/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 8/27/2024 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 9/6/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/16/2024 | Corrections Issued | CRAIG DAVIS |
| Masonry Wall/Backfill | 9/16/2024 | Partial Inspection | CRAIG DAVIS |
| Structural Steel Frame | 9/16/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 9/23/2024 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 9/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 9/27/2024 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 9/27/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 10/23/2024 | Approved | BRENDAN MORELLI |
| Green Building Rough | 10/23/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 10/23/2024 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 10/23/2024 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 11/4/2024 | Approved | CRAIG DAVIS |
| Wood Frame | 11/4/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 11/13/2024 | Approved | CRAIG DAVIS |
| Wood Frame | 11/13/2024 | Approved | CRAIG DAVIS |
| Insulation | 11/19/2024 | Corrections Issued | SABAS ALONSO |
| Insulation | 12/2/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Insulation | 12/9/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Rough | 12/11/2024 | Approved | ANTHONY RAMOS |
| Insulation | 12/11/2024 | Approved | ANTHONY RAMOS |
| HVAC-Rough | 12/13/2024 | Approved | CRAIG DAVIS |
| Insulation | 12/13/2024 | Approved | CRAIG DAVIS |
| Drywall Nailing | 12/24/2024 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 1/7/2025 | Not Ready for Inspection | BARRY HACHE |
| Drywall Nailing | 1/10/2025 | Approved | BARRY HACHE |
| HVAC-Final | 4/8/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 4/8/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 4/14/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 4/17/2025 | Approved | BARRY HACHE |
| Final | 4/17/2025 | Corrections Issued | BARRY HACHE |
| Green Building Final | 4/17/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 4/21/2025 | Approved | BARRY HACHE |
| Final | 4/21/2025 | Conditional Approval | BARRY HACHE |
| Green Building Rough | 4/21/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Approved | BARRY HACHE |
| Service/Power Release | 4/21/2025 | Approved | BARRY HACHE |
| Smoke Detectors | 4/21/2025 | Approved | BARRY HACHE |