3555 S GRAND VIEW BLVD 90066
Certificate Information: 3555 S GRAND VIEW BLVD 90066
- Application / Permit
- 23014-30000-01747
- Plan Check / Job No.
- B23WL01184
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addtion and Remodel to (E) SFD w/Attached Garage. Per engineering design.
- Permit Issued
- Issued on 10/10/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | ALFREDO JARA |
| Building Plans Picked Up | 6/21/2023 | APPLICANT |
| Corrections Issued | 8/16/2023 | ALFREDO JARA |
| Plan Check Approved | 9/29/2023 | DAVID CASTILLO |
| Issued | 10/10/2023 | APPLICANT |
| CofO in Progress | 10/18/2024 | DANIEL VERA |
| Permit Finaled | 11/5/2024 | RICHARD STEINBACH |
| CofO Issued | 11/5/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/5/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/12/2023 | ALFREDO JARA |
| Specific Plan | Cleared | 7/19/2023 | FREDDY GARCIA |
| Low Impact Development (LID) | Cleared | 8/14/2023 | ERNEST TSE |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2023 | JASON NG |
| Sewer availability | Cleared | 8/15/2023 | JASON NG |
| Roof/Waste drainage to street | Cleared | 9/26/2023 | HISASHI KOBAYAKAWA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Rivera Home Builders; Lic. No.: 1080029-B | 14913 BAYOU AVE BELLFLOWER, CA 90706 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/1/2023 | Approved | JESUS PINEDA |
| Deputy Steel/Welding | 11/8/2023 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Corrections Issued | JESUS PINEDA |
| Deputy Wood Construction | 12/20/2023 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 1/4/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 1/4/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 1/4/2024 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 1/10/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 1/10/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 1/10/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 1/10/2024 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 1/10/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 1/22/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 1/22/2024 | Approved | JESUS PINEDA |
| Insulation | 1/22/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 2/2/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 2/2/2024 | Approved | BEN MOLSTAD |
| Shower Pan | 2/2/2024 | Approved | BEN MOLSTAD |
| Pre-Inspection | 3/4/2024 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 8/6/2024 | Approved | JESUS PINEDA |
| Final | 8/6/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 8/6/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 8/6/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 8/6/2024 | Approved | JESUS PINEDA |
| Smoke Detectors | 8/6/2024 | Corrections Issued | JESUS PINEDA |
| Final | 9/24/2024 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 9/24/2024 | Approved | DANIEL VERA |
| Smoke Detectors | 9/24/2024 | Approved | DANIEL VERA |
| Final | 10/15/2024 | Corrections Issued | DANIEL VERA |
| Final | 10/18/2024 | OK to Issue CofO | DANIEL VERA |