12871 W BONAPARTE AVE 90066
Certificate Information: 12871 W BONAPARTE AVE 90066
- Application / Permit
- 23014-30000-01639
- Plan Check / Job No.
- B23WL01100
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 2/6/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | SELLA BENYAMIN |
| Corrections Issued | 5/25/2023 | SELLA BENYAMIN |
| Quality Review Completed | 5/25/2023 | STEVEN KIM |
| Building Plans Picked Up | 6/1/2023 | APPLICANT |
| Plan Check Approved | 1/30/2024 | SELLA BENYAMIN |
| Issued | 2/6/2024 | APPLICANT |
| CofO in Progress | 6/12/2025 | RUBEN RIVAS |
| Permit Finaled | 6/17/2025 | RICHARD STEINBACH |
| CofO Issued | 6/17/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/17/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/9/2023 | DINAH GARIN |
| Low Impact Development (LID) | Cleared | 12/22/2023 | PATRICK LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2024 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 1/17/2024 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Gafco Builders Inc; Lic. No.: 1103935-B | 220 NEWPORT CENTER DRIVE SUITE 104 NEWPORT BEACH, CA 92660 |
| Engineer | Bonaldo,, Serge Vincent; Lic. No.: C43812 | 6875 TRINITY PL ALTA LOMA, CA 91701 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/11/2024 | Approved | TEMISTOCLES CAAL |
| Deputy Reinf. Concrete | 4/17/2024 | Conditional Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/22/2024 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2024 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 4/26/2024 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Steel/Welding | 5/3/2024 | Conditional Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 6/18/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Gas Test | 6/18/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Rough | 6/18/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 6/18/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 6/24/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Approved | TEMISTOCLES CAAL |
| Gas Test | 6/24/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 6/24/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 6/24/2024 | Approved | TEMISTOCLES CAAL |
| Reinforced Concrete Frame | 6/25/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 6/27/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 6/27/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 6/27/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 6/27/2024 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 7/3/2024 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/30/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 7/30/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 7/30/2024 | Approved | SEAN HAUPT |
| METHANE-Rough | 7/30/2024 | Approved | SEAN HAUPT |
| Insulation | 8/2/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 8/8/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 8/28/2024 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 12/2/2024 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 2/19/2025 | Approved | MICHAEL ALLEN |
| Final | 2/19/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 2/19/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 2/19/2025 | Approved | MICHAEL ALLEN |
| Final | 4/17/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Green Building Final | 4/17/2025 | Approved | RUBEN RIVAS |
| METHANE-Final | 4/17/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 4/17/2025 | SGSOV Not Ready | RUBEN RIVAS |
| Smoke Detectors | 4/17/2025 | Approved | RUBEN RIVAS |
| Final | 6/12/2025 | OK to Issue CofO | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Approved | RUBEN RIVAS |